Mynydd y Gwynt Wind Farm

Enquiry received via email

Mynydd y Gwynt Wind Farm

20/01/2011
Gillian Foulkes

Ymholiad

Enquirer contacted the applicant, REH, some time ago but is still awaiting a response.

Cyngor a roddwyd

Advised that we have contacted REH who will be providing us with new contact details to be used to update our website. In the meantime, REH wish to contact you directly.
It is also worth while contacting your local authority, Powys County Council, if you have concerns about the adequacy of consultation.
Any residual concerns the local authority holds could be contained in an 'adequacy of consultation' representation submitted to the IPC. The Planning Act 2008 makes express provision for any representation made by a relevant local authority, which gives the view on how far the promoter complied with the requirements for pre-application consultation. The IPC must have regard to any such adequacy of consultation representation, before making a decision to accept or reject the application.