Hirwaun Power Station

Mae’r dudalen hon yn gosod allan yr amserlen ar gyfer archwilio’r cais. Mae’n cynnwys y terfynau amser ar gyfer gwneud cyflwyniadau i’r Arolygiaeth Gynllunio a dyddiadau digwyddiadau a gynhelir yn ystod yr Archwiliad. Yn ogystal, mae Amserlen yr Archwiliad wedi’i gosod allan yn yr atodiad i’r llythyr rheol 8 a anfonwyd at Bartïon â Buddiant ar ddechrau’r Archwiliad.

Dyddiad digwyddiadDisgrifiad
 Date Passed
23/07/2014
Archwiliad yn dechrau
 Date Passed
21/08/2014
Deadline 1
Deadline for receipt of:
(i) Local impact reports (LIR) from any local authorities (see s60 of the Planning Act 2008)
(ii) Responses to ExA’s first written questions
(iii) Comments on relevant representations (RRs)
(iv) Summaries of all RRs exceeding 1500 words
(v) Written representations (WRs) by all interested parties
(vi) Summaries of all WRs exceeding 1500 words
(vii) Comments on any submissions received prior to the preliminary meeting (see Annex C to this letter)
(viii) Submissions from interested parties recommending locations or items for the itinerary for the accompanied site visit
(ix) Comments on whether the applicant’s additional/replacement documents submitted before the preliminary meeting constitutes a material change to the application (see Annex C)
(x) Any further information requested by the ExA for this deadline
Notifications
(xi) Notification by interested parties of wish to be heard at an open floor hearing
(xii) Notification of wish to be heard at a compulsory acquisition hearing
(xiii) Notification by interested parties of wish to attend and/or make oral representations at all hearings scheduled in the timetable
(xiv) Notification by interested parties of their intention to attend the accompanied site visit
(xv) Notification by statutory parties of wish to be considered an interested party
View the documents received relating to this deadline
 Date Passed
10/09/2014
Deadline 2
Deadline for receipt of:
(i) Comments on responses to ExA’s first written questions
(ii) Responses to comments on RRs
(iii) Comments on WRs
(iv) Responses to comments on any additional representations and submissions received prior to the preliminary meeting
(v) Responses to comments on whether the applicant’s additional/replacement documents submitted before the preliminary meeting constitutes a material change to the application
(vi) Any revised draft DCO from applicant
(vii) Any further information requested by the ExA for this deadline
(viii) Statements of Common Ground (SoCG) requested by the ExA – see note of Preliminary Meeting
View the documents received relating to this deadline
 Date Passed
16/09/2014
Deadline 3
Deadline for receipt of:
(i) Comments on LIRs
(ii) Responses to comments on WRs
View the documents received relating to this deadline
 Date Passed
22/09/2014
Site Visit (Accompanied)
- Meet at 10.30am at the Ty Newydd Country Hotel Car Park
 Date Passed
22/09/2014
Open Floor Hearing
- 6.30pm at Ty Newydd Country Hotel (doors open at 6pm)
 Date Passed
23/09/2014
Issue Specific Hearing 1
Issue specific hearing on draft DCO
- 10am at Ty Newydd Country Hotel (doors open at 9.30am)
 Date Passed
24/09/2014
Compulsory Acquisition Hearing
Compulsory acquisition hearing
- 10am at Ty Newydd Country Hotel (doors open at 9.30am)
 Date Passed
24/09/2014
Issue Specific Hearing 2
Issue specific hearing on environmental matters (including Environmental Impact Assessment (EIA) and Habitats Regulations Assessment (HRA))
- 2pm at Ty Newydd Country Hotel (doors open at 1.30pm)
 Date Passed
25/09/2014
Issue Specific Hearing 3
Reserved for issue specific hearing on environmental matters (including Environmental Impact Assessment (EIA) and Habitats Regulations Assessment (HRA)) of required.
10am at Ty Newydd Country Hotel (doors open at 9.30am)
 Date Passed
07/10/2014
Deadline 4
Deadline for receipt of:
(i) Applicant’s final preferred draft DCO
(ii) Updated SoCGs
(iii) Any information requested by the ExA at the hearings
(iv) Written summaries of oral cases put at hearings
(v) Any further information requested by the ExA for this deadline
View the documents received relating to this deadline
 Date Passed
21/10/2014
(i) ExA’s Report on Implications for European Sites (RIES) to be published
(ii) ExA’s second written questions to be published
 Date Passed
30/10/2014
Deadline 5
Deadline for receipt of:
(i) Comments on applicant’s final preferred draft DCO
(ii) Any further information requested by the ExA for this deadline
View the documents received relating to this deadline
 Date Passed
13/11/2014
Deadline 6
Deadline for receipt of:
(i) Comments on the RIES
(ii) Responses to ExA’s second written questions
 Date Passed
25/11/2014
Deadline 7
Deadline for receipt of:
(i) Responses to comments on applicant’s final preferred draft DCO
(ii) Any further information requested by the ExA for this deadline
 Date Passed
23/01/2015
Archwiliad wedi cau