Mynydd y Gwynt Wind Farm

Enquiry received via phone

Mynydd y Gwynt Wind Farm

09/02/2011
FBA Group - Angharad Jones

Ymholiad

Enquirer is currently researching about the pre-application consultation process and asked:
Which section within the Act details the duty to publicise the proposed application and what is the minimum timeframe for consultation responses?

Cyngor a roddwyd

s48 of the Act states that an applicant must publicise the proposed application. The publication must include a deadline for the receipt of responses to the publicity (min 28 day time frame).
Forwarded links to secondary legislation and guidance which related to pre-application consultation.