Brechfa Forest West Wind Farm

Enquiry received via email

Brechfa Forest West Wind Farm

29/08/2012
Grwp Blaengwen

Ymholiad

With regards Grwp Blaengwen's response to the new draft DCO.

Cyngor a roddwyd

The comments made on behalf of Grwp Blaengwen on the draft Development Consent Order (DCO) dated 9 August 2012 contain on page 4 a question about a possible future draft DCO. For the avoidance of doubt, please be advised that the examination timetable does not provide for a further revised draft DCO to be issued and as far as we are aware the Examining Authority does not intend to issue a further revised draft DCO.