What happens next
Dates for the Examination can be viewed on the Examination Timetable page.
Notice of the Procedural Decision has been issued by the Examining Authority to Interested Parties in the Rule 8 letter; this includes information about how the Examination will be conducted and the Examination Timetable as currently set out.
20/09/2023 - Deadline for close of examination, Examination ends20/12/2023 - Deadline for Planning Inspectorate to submit recommendation. See the Examination Timetable for further information.
If you have a legal interest in land affected by a Nationally Significant Infrastructure Project and:
- have not been identified by the Applicant; and
- did not register to become an Interested Party;
then you can make a request to the Examining Authority to become an Interested Party under s102A of the Planning Act 2008.
Timeline (34 items)

The Examining Authority (ExA) has exercised its discretion to accept the following Additional Submission:
- Fisher German LLP on behalf of John Williams (PDF, 196 KB)
The Examination Library (PDF, 608 KB) has been updated.
Following the Examining Authority’s (ExA) decision to accept the Applicant’s change request dated 27 March 2023 for examination, comments are now invited on the Applicant’s proposed provision for the compulsory acquisition of additional land by 23:59 on 14 June 2023.
Any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s proposed provision only. Any submissions that are not in relation to this, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

The Deadline 3 submissions have been published.
The Examination Library (PDF, 605 KB) has been updated.
Following the Examining Authority’s (ExA) decision to accept the Applicant’s change request dated 27 March 2023 for examination, comments are now invited on the Applicant’s proposed provision for the compulsory acquisition of additional land by 23:59 on 14 June 2023.
Any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s proposed provision only. Any submissions that are not in relation to this, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

The Examining Authority has published the following documents:
Issue Specific Hearing 1 agenda (PDF, 203 KB);
Compulsory Acquisition Hearing agenda (PDF, 204 KB); and
Issue Specific Hearing 2 agenda (PDF, 138 KB).
The Examination Library (PDF, 553 KB) will be updated shortly.
Following the Examining Authority’s (ExA) decision to accept the Applicant’s change request dated 27 March 2023 for examination, comments are now invited on the Applicant’s proposed provision for the compulsory acquisition of additional land by 23:59 on 14 June 2023.
Any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s proposed provision only. Any submissions that are not in relation to this, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

We have recently been informed that a Deadline 2 submission from Natural Resources Wales (PDF, 172KB) was inadvertently omitted from publishing on 12 May 2023. This has now been published.
Following the Examining Authority’s (ExA) decision to accept the Applicant’s change request dated 27 March 2023 for examination, comments are now invited on the Applicant’s proposed provision for the compulsory acquisition of additional land by 23:59 on 14 June 2023.
Any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s proposed provision only. Any submissions that are not in relation to this, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

The Deadline 2 submissions have been published.
The Examination Library (PDF, 552KB) has been updated.
Following the Examining Authority’s (ExA) decision to accept the Applicant’s change request dated 27 March 2023 for examination, comments are now invited on the Applicant’s proposed provision for the compulsory acquisition of additional land by 23:59 on 14 June 2023.
Any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s proposed provision only. Any submissions that are not in relation to this, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

Following the Examining Authority’s (ExA) decision to accept the Applicant’s change request dated 27 March 2023 for examination, comments are now invited on the Applicant’s proposed provision for the compulsory acquisition of additional land by 23:59 on 14 June 2023.
Any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s proposed provision only. Any submissions that are not in relation to this, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.
Please note that the following date reserved for a hearing in the Examination Timetable is no longer required and the event has now been cancelled:
9 June 2023 – Open Floor Hearing (OFH)
The OFH will be rescheduled later in the Examination, if required.

The Examining Authority (ExA) has exercised its discretion to accept the following Additional Submission:
- Liverpool Bay CCS Limited – D.7.20 Notification of Intention to Submit a Change Request 2 (PDF, 496 KB)
Please note, the publication of any letter or supporting documentation relating to the proposed change does not indicate that the change has been accepted by the ExA. Any comments/ responses on the merits of the application should be made in respect of the application as it was originally submitted.
The ExA has issued a Procedural Decision and written to the Applicant (PDF, 156KB) in response to the Notification of Intention to Submit a Change Request 2.
The Examination Library (PDF, 530 KB) has been updated.

The Examining Authority has exercised its discretion to accept the following Additional Submission:
- Additional Submission – Canal and River Trust (PDF, 185 KB)
The Examination Library (PDF, 529 KB) has been updated.

The Deadline 1A submissions have been published.
The Examination Library (PDF, 528 KB) has been updated.

We have recently been informed that a Deadline 1 submission from Peel NRE – Written Representation Appendices 1-17 (PDF, 39 MB) was inadvertently omitted from publishing on 19 April 2023. This has now been published.
The Examining Authority has exercised its discretion to accept the following Additional Submission from a non-Interested Party:
- Additional Submission – Stephen Gibbins (PDF, 28 MB)
The Examination Library (PDF, 524 KB) has been updated.

The Examining Authority has exercised its discretion to accept the following Additional Submissions:
- Applicant’s request for change/additional land application (PDF, 556 KB); and
- Applicant’s supporting documents (Examination Library references CR-001 to CR-126).
The following documents have been published:
- Examining Authority’s Procedural Decision letter to accept the Applicant’s change request (PDF, 192 KB); and
- Examining Authority’s Proposed Provision checklist (PDF, 137 KB).
The Applicant must now publicise and give notice of the Proposed Provisions the change request accepted by the ExA, as required by Regulation 7 and 8 of the Infrastructure Planning (Compulsory Acquisition) Regulations 2010.
A date confirming when Interested Parties will have the opportunity to make comments on these changes will be announced shortly.
The Examination Library (PDF, 522 KB) has been updated.

The Examining Authority has exercised its discretion to accept the following Additional Submissions:
- United Utilities Water Limited – Comments on the Preliminary Environmental Information Report (PDF, 179 KB);
- United Utilities Water Limited – Response to ExA’s ExQ1 (PDF, 219 KB); and
- United Utilities Water Limited – Standard Conditions for Works Adjacent to Pipelines (PDF, 902 KB).
The Examination Library (PDF, 438 KB) has been updated.

The Deadline 1 submissions have been published.
The Examination Library (PDF, 435 KB) has been updated.

The following documents have been published:
- The Examination Timetable (Rule 8 letter) (PDF, 489 KB)
- The Examining Authority’s First Written Questions. (PDF, 779 KB) The Deadline for responses is Deadline 1: Monday 17 April 2023.
The Examination Library (PDF, 386 KB) has been updated.

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties
Procedural decision following Preliminary Meeting

The Examining Authority (ExA) has exercised its discretion to accept the following Additional Submission:
- Liverpool Bay CCS Limited – D.7.5 Notification of Intention to Submit a Change Request (PDF, 507 KB)
Please note, the publication of any letter or supporting documentation relating to the proposed change does not indicate that the change has been accepted by the ExA. Any comments/ responses on the merits of the application should be made in respect of the application as it was originally submitted.
The Examination Library (PDF, 383 KB) has been updated.

The recording and transcript of the Preliminary Meeting held on 20 March 2023 have now been published.
The Examination Library (PDF, 370 KB) has been updated.

To watch without simultaneous translation: https://www.liveeventstream.online/planning-inspectorate-hearings/cy-hynet-carbon-dioxide-pipeline
To watch with simultaneous translation from Welsh to English: https://www.liveeventstream.online/planning-inspectorate-hearings/en-hynet-carbon-dioxide-pipeline
The Examining Authority has exercised its discretion to accept the following Additional Submissions that supersede previous versions:
- Liverpool Bay CCS Limited – D.6.3.9.3 Environmental Statement – Appendix 9.3 – Bat Activity Survey Report Part 1 (Clean) (PDF, 45 MB);
- Liverpool Bay CCS Limited – D.6.3.9.3 Environmental Statement – Appendix 9.3 Bat Activity Survey Report Part 1 (Tracked Changes) (PDF 45 MB); and
- Liverpool Bay CCS Limited – D.6.3.9.4 Appendix 9.4 Bats and Hedgerows Assessment Rev B Part 3 (PDF 48 MB).
The Examination Library (PDF, 374 KB) has been updated.

- Preliminary Meeting takes place
- Examination begins

For those wishing to observe the Preliminary Meeting that will be held on 20 March 2023, here are the links to the livestream (which remain the same for all Hearings relating to this project):
To watch without simultaneous translation: https://www.liveeventstream.online/planning-inspectorate-hearings/cy-hynet-carbon-dioxide-pipeline
To watch with simultaneous translation from Welsh to English: https://www.liveeventstream.online/planning-inspectorate-hearings/en-hynet-carbon-dioxide-pipeline

The Examining Authority has exercised its discretion to accept Additional Submissions from the Applicant relating to remaining additional information requested in the Section 51 advice from the Planning Inspectorate dated 31 October 2022 (PDF, 138KB).
The Examination Library (PDF, 365KB) has been updated.

Submissions for Procedural Deadline A have now been published and added to the Examination Library (PDF, 336 KB)

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

Following appointment of the Examining Authority on 17 January 2023, the documents below have now been formally accepted by the Examining Authority and published as Additional Submissions:
- Applicant’s Response to s51 Advice – Cover Letter(PDF, 537 KB)
- Applicant’s Response to s51 Advice – Application Form(PDF, 160 KB)
- Applicant’s Response to s51 Advice – Application Document Tracker (PDF, 706 KB)
- Applicant’s Response to s51 Advice – Appendix 18 – Part 1(PDF, 37 MB)
- Applicant’s Response to s51 Advice – Appendix 18 – Part 2(PDF,47 MB)
- Applicant’s Response to s51 Advice – Appendix 18 – Part 3(PDF, 41 MB)
The Examining Authority carried out Unaccompanied Site Inspections on Tuesday 15 November 2022 (PDF, 86KB) and Wednesday 16 November 2022.(PDF, 70KB) The notes have now been published.
These have been added to the Examination Library (PDF, 272KB).




The Applicant has submitted the following documents:
- Applicant’s Response to s51 Advice – Cover Letter (PDF, 537 KB)
- Applicant’s Response to s51 Advice – Application Form (PDF, 160 KB)
- Applicant’s Response to s51 Advice – Application Document Tracker (PDF, 706 KB)
- Applicant’s Response to s51 Advice – Appendix 18 – Part 1 (PDF, 37 MB)
- Applicant’s Response to s51 Advice – Appendix 18 – Part 2 (PDF,47 MB)
- Applicant’s Response to s51 Advice – Appendix 18 – Part 3 (PDF, 41 MB)
A decision on whether these will be accepted into the Examination will be made once the Examining Authority has been appointed.
These have been added to the Examination Library (PDF, 265KB).


The application was received by the Planning Inspectorate on 03 October 2022.
The application documents will be made available on the project page of this website if the application is accepted for examination.
It is for the Applicant to decide whether or not application documents can be published upon submission (see government’s Planning Act 2008: guidance on the Pre-application process).