A30 Chiverton to Carland Cross Scheme

What happens next

A decision on the application for a Development Consent Order for A30 Chiverton to Carland Cross Scheme was taken on 06 February 2020 and has now been issued.

The period for legal challenge is defined in s118 of the Planning Act 2008. Further information about legal challenge can be found in the letter sent to all Interested Parties accompanying the Secretary of State’s decision and statement of reasons.

If you have any queries about the process please email the Planning Inspectorate at [email protected] or telephone the helpline on 0303 444 5000.

Timeline (39 items)

The Secretary of State has granted development consent for this application. For further information please refer to the following decision documentation:

Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Recommendation Report

06 February 2020
Decision made by the Secretary of State
06 February 2020
13 December 2019

The Secretary of State has issued a letter seeking further clarification from the Applicant, Scottish Power Renewables (UK) and Western Power Distribution. The deadline for responses is the 12 December 2019.

28 November 2019
Recommendations given by the Planning Inspectorate
06 November 2019

Notification of completion of The Examining Authority’s Examination Letter (Section 99) has been published.

07 August 2019

The Examination closed at 23:59 on 6 August 2019.

06 August 2019

The Submissions for Deadline 9 have now been published.

05 August 2019

The Submissions for Deadline 8 have now been published.

29 July 2019
22 July 2019

The Submissions for Deadline 7 have now been published.

16 July 2019

The Submissions for Deadline 6 have now been published.

09 July 2019
01 July 2019

The Submissions for Deadline 5 have now been published.

20 June 2019

The Action Points and Audio recordings from the Issue Specific Hearing on Chybucca junction 12 June 2019 have now been published.

13 June 2019

The Submissions for Deadline 4 have now been published.

02 May 2019

The Submissions for Deadline 3 have now been published.

26 April 2019

The Audio and Action Points for Compulsory Acquisition Hearing 1 and Issue Specific Hearings 2 and 3 have now been published.

09 April 2019

Next week’s hearing agendas and the Accompanied Site Inspection itinerary have now been published.

26 March 2019

The Submissions for Deadline 2 have now been published.

20 March 2019

The Submissions for Deadline 1 have now been published.

21 February 2019

Read the letter

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties

Procedural decision following Preliminary Meeting

13 February 2019

A position statement between Highways England and Scottish Power Renewables, accepted at the discretion of the Examining Authority at the Preliminary Meeting, and both the Preliminary Meeting and Issue Specific Hearing 1 audio have been published.

07 February 2019
  • Preliminary Meeting takes place
  • Examination begins
06 February 2019

The Applicant’s updated documents submitted in response to section 51 advice have been published.

 

24 January 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

09 January 2019
Relevant representations published on the website
15 November 2018
Registration of interested parties closes
10 November 2018
Registration of interested parties begins
04 October 2018
Read the letter

The application has been accepted for examination

27 September 2018
Decision on whether or not to accept the application for examination
27 September 2018

This application was received by the Planning Inspectorate on 30 August 2018.

The Applicant has agreed that all application documents can be published as soon as practicable to help everyone become familiar with the detail of what is being proposed in this application. The Planning Inspectorate will therefore make the application documents available as soon as practicable.

This provision is solely for the purpose of allowing more time to all those who wish to become familiar with the detail of what is being proposed ahead of the Relevant Representation period without lengthening the overall time required for the application process. There will be no opportunity at this stage to make comments on the application. However, if the application is accepted anyone interested in the application will be able to register and express their views during the Relevant Representation stage and the subsequent examination

31 August 2018
Application received by the Planning Inspectorate
30 August 2018