Cambridge Waste Water Treatment Plant Relocation

What happens next

The application is expected to be submitted to the Planning Inspectorate Q1 2023.

After receipt of the application, there will be 28 days for the Planning Inspectorate to review the application and decide whether or not to accept it for examination.

If the application is accepted, we will confirm the timescale within which people can register to become an Interested Party by making a Relevant Representation.

If the application is accepted, we will:

  • Publish all the application documents on this project page.
  • Publish the date from which you will be able to register to put your case on the application.
  • Publish the date on which the registration period will close.

Timeline (3 items)

Deadline to accept or not accept the application
28 February 2023

The application has been withdrawn. Please see the Applicant’s letter (PDF, 124 KB).

22 February 2023
Application received by the Planning Inspectorate
31 January 2023