Thames Tideway Tunnel

What happens next

A decision on the application for a Development Consent Order for Thames Tideway Tunnel was taken on 12 September 2014.

Timeline (13 items)

A Decision Letter (PDF, 237KB) and Amendment Order (PDF, 114KB) have been issued by the Department for Environment, Food and Rural Affairs to make a change that is not material to the Thames Tideway Tunnel Development Consent Order.

25 November 2022

Representations received in response to the application for a non-material change to the Thames Tideway Tunnel Development Consent Order have been published.

12 October 2022

An application for a non-material change to the Thames Tideway Tunnel Development Consent Order has been made by Bazalgette Tunnel Limited.

If you wish to make a representation, this should be emailed to [email protected] or posted to:

National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN

The deadline for receipt of representations is 23:59 on Sunday 9 October 2022.

02 September 2022

The Examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

24 February 2021
Decision made by the Secretary of State
12 September 2014
Recommendations given by the Planning Inspectorate
12 June 2014
  • Preliminary Meeting takes place
  • Examination begins
12 September 2013
Relevant representations published on the website
04 June 2013
Registration of interested parties closes
28 May 2013
Registration of interested parties begins
17 April 2013
Decision on whether or not to accept the application for examination
27 March 2013
Application received by the Planning Inspectorate
28 February 2013