Eggborough CCGT

What happens next

27/09/2018 - Deadline for Secretary of State to make decision

The Examining Authority issued a Recommendation Report to the Secretary of State on 27 June 2018. The Secretary of State has three months in which to issue a decision. The decision letter and Recommendation Report will be published on this project page once a decision has been made.

Timeline (31 items)

notice icon

The Secretary of State for Business, Energy and Industrial Strategy has requested further comments from The Crown Estate.

01 August 2018
notice icon

The Secretary of State for Business, Energy and Industrial Design requesting comments from the Applicant, The Crown Estate and Northern Gas Limited.

09 July 2018
milestone icon
Recommendations given by the Planning Inspectorate
27 June 2018
notice icon

Submissions for Deadline 9 (14 March 2018) have  been published.

 

15 March 2018
notice icon
01 March 2018
notice icon
15 February 2018
notice icon
01 February 2018
notice icon

The Report on the Implications for European Sites (RIES) and a Request for further information from the Examining Authority have been published.

Responses are to be received by Deadline 7 – Wednesday 14 February 2018

26 January 2018
notice icon

Documents received for Deadline 5 (09 January 2018) have been published.

10 January 2018
notice icon

Documents received for Deadline 4 (21 December 2017) have been published.

22 December 2017
notice icon

The Examining Authority’s Further Written Questions have been published.

14 December 2017
notice icon

The Examination Authority has accepted a submission dated 8 December 2017 from Hensall Parish Council as a late deadline three submission.

11 December 2017
notice icon

A Rule 8(3) and Rule 17 letter has been published, requesting further information and changes to the timetable.

05 December 2017
notice icon

Documents received for Deadline 3 (30 November 2017) have been published.

01 December 2017
notice icon

Action Points from the Issue Specific Hearing on Environmental Matters have been published.

Audio recordings of the hearings on 22 and 23 November 2017 have also been published.

24 November 2017
notice icon
02 November 2017
notice icon
12 October 2017
milestone icon Read the letter

The examination timetable (Rule 8 letter) has been sent to interested parties

Procedural decision following Preliminary Meeting

04 October 2017
milestone icon
  • Preliminary Meeting takes place
  • Examination begins
27 September 2017
milestone icon

The notification of Preliminary Meeting (rule 6 letter) has been sent Read the letter

The letter also includes the draft timetable for examination of the application and statement of principal issues.

30 August 2017
milestone icon
Relevant representations published on the website
18 August 2017
milestone icon
Registration of interested parties closes
09 August 2017
milestone icon
Registration of interested parties begins
29 June 2017
milestone icon Read the letter

The application has been accepted for examination

27 June 2017
milestone icon
Decision on whether or not to accept the application for examination
27 June 2017
milestone icon
Application received by the Planning Inspectorate
30 May 2017