Willington C Gas Pipeline

What happens next

A decision on the application for a Development Consent Order for Willington C Gas Pipeline was taken on 17 December 2014.

Timeline (11 items)

The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

24 December 2019
Decision made by the Secretary of State
17 December 2014
Recommendations given by the Planning Inspectorate
02 October 2014
Examination ends

02 July 2014
  • Preliminary Meeting takes place
  • Examination begins
10 January 2014
Relevant representations published on the website
17 October 2013
Registration of interested parties closes
11 October 2013
Registration of interested parties begins
04 September 2013
Decision on whether or not to accept the application for examination
22 August 2013
Application received by the Planning Inspectorate
30 July 2013