Hornsea Offshore Wind Farm (Zone 4) – Project One

What happens next

A decision on the application for a Development Consent Order for Hornsea Offshore Wind Farm (Zone 4) - Project One was taken on 10 December 2014.

Timeline (12 items)

The Marine Management Organisation has published notices of variation to the Deemed Marine Licences.

07 November 2022

The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

29 January 2020
Decision made by the Secretary of State
10 December 2014
Recommendations given by the Planning Inspectorate
10 September 2014
  • Preliminary Meeting takes place
  • Examination begins
10 December 2013
Relevant representations published on the website
24 October 2013
Registration of interested parties closes
23 October 2013
Registration of interested parties begins
05 September 2013
Decision on whether or not to accept the application for examination
22 August 2013
Application expected from applicant
31 July 2013
Application received by the Planning Inspectorate
30 July 2013