Immingham Eastern Ro-Ro Terminal

What happens next

Dates for the Examination can be viewed on the Examination Timetable page.

Notice of the Procedural Decision has been issued by the Examining Authority to Interested Parties in the Rule 8 letter; this includes information about how the Examination will be conducted and the Examination Timetable as currently set out.

25/01/2024 - Deadline for close of examination. See the Examination Timetable for further information.

If you have a legal interest in land affected by a Nationally Significant Infrastructure Project and:

  • have not been identified by the Applicant; and
  • did not register to become an Interested Party;

then you can make a request to the Examining Authority to become an Interested Party under s102A of the Planning Act 2008.

Timeline (33 items)

The recordings and transcripts for Issue Specific Hearing 3 (ISH3)Issue Specific Hearing 4 (ISH4) and Compulsory Acquisition Hearing 1 (CAH1) have been published.

The Examination Library (PDF, 433KB) has been updated.

02 October 2023

The Examining Authority has accepted an Additional Submission from the Applicant – Draft DCO: Requirement 18 – Impact protection measures and associated indicative plan (PDF, 367KB)

Instructions have been sent to those who have registered to participate in the events scheduled for Thursday 28 September 2023 which comprise of: continuation of Issue Specific Hearing 3 (ISH3) commencing at 10:00, Issue Specific Hearing 4 (ISH4) commencing at 15:00 and Compulsory Acquisition Hearing 1 (CAH1) commencing at 18:00.

Anyone who wishes to observe the events in real time should use the following link: https://www.sparq.live/tr030007

Please note that all hearings on Thursday 28 September 2023 can be watched via the same link, the event will start streaming when opened by the Examining Authority. If the Livestream does not initially work, it may be resolved by refreshing the webpage.

28 September 2023

Instructions have been sent to those who have registered to participate in the events scheduled for Thursday 28 September 2023 which comprise of: continuation of Issue Specific Hearing 3 (ISH3) commencing at 10:00, Issue Specific Hearing 4 (ISH4) commencing at 15:00 and Compulsory Acquisition Hearing 1 (CAH1) commencing at 18:00.

Anyone who wishes to observe the events in real time should use the following link: https://www.sparq.live/tr030007

Please note that all hearings on Thursday 28 September 2023 can be watched via the same link, the event will start streaming when opened by the Examining Authority. If the Livestream does not initially work, it may be resolved by refreshing the webpage.

27 September 2023

Instructions have been sent to those who have registered to participate in the Issue Specific Hearing 3 (ISH3) scheduled for Wednesday 27 September 2023.

An email shall be sent on Wednesday 27 September to those parties that have registered to participate in Issue Specific Hearing 3 (ISH3) continued, Issue Specific Hearing 4 (ISH4) and Compulsory Acquisition Hearing 1 (CAH1) scheduled for Thursday 28 September 2023.

Anyone who wishes to observe the events in real time should use the following link: https://www.sparq.live/tr030007

Please note that the event will start streaming when opened by the Examining Authority. If the Livestream does not initially work, it may be resolved by refreshing the webpage.

26 September 2023
20 September 2023

The following documents have been published:

Agenda for Issue Specific Hearing 3 (ISH3) (PDF 133KB)

Accompanied Site Inspection itinerary – 26 September 2023 (PDF 167KB)

The Examination Library (PDF 411KB) has been updated.

19 September 2023

The Examining Authority’s Further Written Questions (EXQ2) (PDF, 332KB) have been published.

The Deadline for response is Monday 9 October 2023, Deadline 4.

The Examination Library (PDF, 411KB) has been updated.

15 September 2023

The Deadline 3 (D3) submissions have been published.

The Examination Library (PDF, 409KB) has been updated.

12 September 2023

The Deadline 2 (D2) submissions have been published.

The Examination Library (PDF, 387KB) has been updated.

07 September 2023

The Examining Authority’s notification of Hearings and an Accompanied Site Inspection (ASI) (PDF, 197KB) has been published.

The Examination Library (PDF, 329KB) has been updated.

30 August 2023

The Examining Authority’s request for Further Information (PDF, 134KB) from North East Lincolnshire Council has been published. The Deadline for response is Deadline 2 – 5 September 2023

The Examination Library (PDF, 327KB) has been updated.

24 August 2023

The Deadline 1 (D1) submissions have been published.

The Examination Library (PDF, 325KB) has been updated

17 August 2023

The Note of the Familiarisation Site Inspection (PDF, 147KB) has been published.

The Examination Library (PDF, 292KB) has been updated.

11 August 2023

The Examining Authority’s First Written Questions (PDF, 379KB) have been published.

The Examination Library (PDF, 290KB) has been updated.

08 August 2023

The Following documents have been published:

The Examination Library (PDF 288KB) has been updated.

02 August 2023

Read the letter

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties

Procedural decision following Preliminary Meeting

02 August 2023

The recordings and transcripts for the Preliminary Meeting, Issue Specific Hearing 1 (ISH1) and Issue Specific Hearing 2 (ISH2) have been published.

The Examination Library (PDF, 271KB) has been updated.

01 August 2023

Instructions have been sent to those who have registered to participate in participate in Issue Specific Hearing 2 (ISH2) scheduled for Thursday 27 July 2023.

Anyone who wishes to observe the events in real time should use the following link: https://www.sparq.live/tr030007

Please note that the event will start streaming when opened by the Examining Authority. If the Livestream does not initially work, it may be resolved by refreshing the webpage.

Two submissions from DFDS Seaways Plc which were made for Procedural Deadline A have been published. These submissions submitted on time for the deadline but were missed previously due to a technical error.

26 July 2023
  • Preliminary Meeting takes place
  • Examination begins
25 July 2023

Instructions have been sent to those who have registered to participate in the Preliminary Meeting (PM) and Issue Specific Hearing 1 (ISH1) scheduled for Tuesday 25 July 2023.

An email shall be sent on Wednesday 26 July to those parties that have registered to participate in Issue Specific Hearing 2 (ISH2) scheduled for Thursday 27 July 2023.

Anyone who wishes to observe the events in real time should use the following link: https://www.sparq.live/tr030007

Please note that the event will start streaming when opened by the Examining Authority. If the Livestream does not initially work, it may be resolved by refreshing the webpage.

24 July 2023

The Examining Authority has issued a procedural decision in relation to the itinerary for the familiarisation site inspection (PDF, 156KB)

An Additional Submission from Associated British Ports (PDF, 130KB) concerning proposed scheme changes has been accepted at the discretion of the Examining Authority.

20 July 2023

The Agendas for Issue Specific Hearing 1 (PDF, 158KB) on Tuesday 25 July 2023, and Issue Specific Hearing 2 (PDF, 148KB) on Thursday 27 July 2023 are now available.

A letter has been issued to notify of a Change to the appointed Examining Authority (PDF, 133KB).

The Open Floor Hearing, scheduled for 6.00pm on Tuesday 25 July 2023 has been cancelled.

14 July 2023

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

20 June 2023

The Examining Authority has issued Procedural Decisions (PDF, 234KB) relating to the preparation of Statements of Common Ground (SoCGs) and summaries of Principal Areas of Disagreement (PADs).

The Examination Library (PDF,218KB) has been updated.

26 May 2023
Relevant representations published on the website
21 April 2023
Registration of interested parties closes
19 April 2023

The Examining Authority has accepted 8 Additional Submissions from the Applicant:

The acceptance of the additional submissions will be addressed in the Examining Authority’s forthcoming Rule 6 letter and parties will have an opportunity to submit further written representations during the examination about these additional submissions alongside other matters.

To register as an Interested Party and have your say, please complete a registration form online by 19 April 2023.  For further advice please see Advice Note 8.2: How to register to participate in an Examination.  You can check our step by step guide to find out more about having your say about a national infrastructure project.

06 April 2023
Registration of interested parties begins
09 March 2023
Read the letter

The application has been accepted for examination

06 March 2023
Decision on whether or not to accept the application for examination
06 March 2023
Application received by the Planning Inspectorate
10 February 2023

The application has been withdrawn. Please see the Applicant’s letter (PDF, 102KB).

01 February 2023

This application was received by the Planning Inspectorate on 5 January 2022.

The application documents will be made available on the project page of this website if the application is accepted for examination.

It is for the Applicant to decide whether or not application documents can be published upon submission (see government’s Planning Act 2008: guidance on the Pre-application process).

10 January 2023