North Wales Wind Farms Connection

You can filter the results to show only the items that match your interest.

Documents Published By Stage

Pre Application (3)

Developer's Application (193)

Acceptance (6)

Pre Examination (19)

Examination (446)

Decision (43)

Decided (2)

Date

SourceDescription
Other
Size: 107 KB
Durand Hotham
Late submission to Deadline 2- This was accepted at the discretion of the Examining Authority
Other
Size: 72 KB
Natural Resources Wales
Late submission to Deadline 2- This was accepted at the discretion of the Examining Authority
Other
Size: 243 KB
Pylon the Pressure Group
Comments on responses to the ExA?s first written questions- Submitted for Deadline 2 of 17 September 2015
Other
Size: 38 KB
SP Manweb
Covering letter - Submitted for the Deadline 2 of 17 September 2015
Other
Size: 1 MB
SP Manweb
Comments on responses to ExA's first written questions. Submitted for Deadline 2 of 17 September 2015
Other
Size: 6 MB
SP Manweb
Further photomontages submitted in accordance with the commitment contained in respect of the ExA?s First Written question 8.15
Other
Size: 140 KB
SP Manweb
Addendum to the Book of reference (version 2) August 2015- Submitted for the Deadline 2 of 17 September 2015
Other
Size: 1,018 KB
Dewi Parry
Response to Applicant?s ?Response to Relevant Representations? Document- Submitted for Deadline 2 of 17 September 2015
Other
Size: 18 KB
Iwan W Jones
Comments on responses to written representations- Submitted for Deadline 2 of 17 September 2015
Other
Size: 70 KB
JP Hughes
Comments on responses to the ExA's first written questions- Submitted for Deadline 2 of 17 September 2015
Other
Size: 20 MB
SP Manweb
Key Plans for Viewpoints in Technical Appendix 7.3 Part A, response to the Examining Authority First Written Question 8.15
Other
Size: 1 MB
SP Manweb
Responses to written representations and Local Impact Report received from Conwy County Borough Council-Submitted for Deadline 2 of 17 September 2015
Other
Size: 1 MB
SP Manweb
Tracked change version of the DCO showing amendments made between version 1 and version 2 of the draft DCO-Submitted for Deadline 2 of 17 September 2015
Other
Size: 28 MB
SP Manweb
Key Plans for Viewpoints in Technical Appendix 7.3 Part C, in response to the Examining Authority First Written Question 8.15
Other
Size: 7 MB
John Mars Jones
Response to Deadline 1 - Submitted for Deadline 2 of 17 September 2015
Other
Size: 63 KB
Jill Tyrer
Written representation - Submitted for Deadline 2 of 17 September 2015
Other
Size: 101 KB
Eifion Bibby
Response to Applicant?s ?Response to Relevant Representations? Document- Submitted for Deadline 2 of 17 September 2015
Other
Size: 613 KB
SP Manweb
Schedule of mitigation. Submitted for Deadline 2 of 17 September 2015
Other
Size: 170 KB
Cefn Meiriadog and Glascoed Road Residents and Users Group
Comments on responses to the ExA's first written questions- Submitted for Deadline 2 of 17 September 2015
Other
Size: 986 KB
SP Manweb
Responses to written representations received- Submitted for Deadline 2 of 17 September 2015
Other
Size: 77 KB
Dafydd I Jones
Comments on responses to the ExA's first written questions- Submitted for Deadline 2 of 17 September 2015
Other
Size: 2 MB
SP Manweb
Revised draft of the DCO (Version 2) (Document reference 3.1 (v.2))-Submitted for Deadline 2 of 17 September 2015
Other
Size: 153 KB
SP Manweb
Statement of Common Ground between SP Manweb and the Local Health Board of North Wales. Submitted for Deadline 2 of 17 September 2015
Other
Size: 31 MB
SP Manweb
Key Plans for Viewpoints in Technical Appendix 7.3 Parts B in response to the Examining Authority First Written Question 8.15
Other
Size: 57 KB
Robin Barlow
Response to Applicant?s ?Response to Relevant Representations? Document- Submitted for Deadline 2 of 17 September 2015
Other
Size: 97 KB
Simon White
Comments on responses to the ExA's first written questions- Submitted for Deadline 2 of 17 September 2015
Other
Size: 71 KB
D E Tyrer
Response to Deadline 1 - Submitted for Deadline 2 of 17 September 2015
Other
Size: 1 MB
SP Manweb
Responses to written representations and Local Impact Report received from Denbighshire County Council-Submitted for Deadline 2 of 17 September 2015
Documents can be filtered by the date they were published or by the deadline date that they relate to. Deadlines are publicised in the examination timetable at the beginning of the examination and can be viewed on the examination timetable tab.