The filtered list shows documents relating to the decision for the development consent order.

SourceDescription
Other
Size: 4 MB
Secretary of State Decision Letter and Statement of Reasons
Decision made by the Secretary of State for Energy and Climate Change, dated 8 December 2015
Other
Size: 553 KB
Development Consent Order as made by the Secretary of State
Development Consent Order as made by the Secretary of State 8 December 2015
Other
Size: 755 KB
Habitats Regulations Assessment
Habitats Regulations Assessment
Other
Size: 108 KB
Notice of the Decision by the Secretary of State (Reg 23)
Letter giving notice of the decision by the Secretary of State for Energy and Climate Change
Other
Size: 2 MB
Examining Authority Recommendation Report and Recommended Development Consent Order
Examining Authority's Recommendation Report and Recommended Development Consent Order
Other
Size: 733 KB
Associated British Ports
Response from Associated British Ports to the request for comments by the Department of Energy and Climate Change in their letter dated 29 October 2015
Other
Size: 505 KB
Duncan O'Connor (Pinsent Masons LLP) on behalf of Tata Steel UK Limited
Response from Tata Steel UK Limited to the request for comments by the Department of Energy and Climate Change in their letter dated 29 October 2015
Other
Size: 191 KB
Louise Edwards on behalf of Natural Resources Wales
Response from Natural Resources Wales to the request for comments by the Department of Energy and Climate Change in their letter dated 29 October 2015
Other
Size: 110 KB
Department for Energy and Climate Change
Letter to the Applicant, Associated British Ports and Natural Resources Wales requesting comments on the application
Other
Size: 524 KB
Sheelagh MacGregor (Pinsent Masons LLP) on behalf of Tata Steel UK Ltd
Revision 2 of Comments on Associated British Port?s response to the ExA?s rule 17 request of 20 May, originally submitted 5 June 2015
Other
Size: 1 MB
Sheelagh MacGregor (Pinsent Masons LLP) on behalf of Tata Steel UK Ltd
Final Submission from the Applicant including the following appendices: Appendix 1 - comparison between Rev 5 and Rev 6 of the draft DCO. Please be aware that this Appendix has been substituted and published separately (under Developer?s Application ? Draft Development Consent Orders) as due to a technical error is not displaying in full within this document. Appendix 2 - comparison between 5 June and 9 June versions of Applicants comments on ABP's response to Rule 17 request for information by the EXA on 20 May 2015. Appendix 3 - joint statement with Network Rail. Appendix 4 - final text of SoCG with NPTCBC.
Other
Size: 263 KB
Sheelagh MacGregor (Pinsent Masons LLP) on behalf of Tata Steel UK Limited
Statement of Common Ground between Tata Steel UK Limited and Neath Port Talbot County Borough Council
Other
Size: 217 KB
Martyn Jarvis (Addleshaw Goddard LLP) on behalf of Network Rail
Joint statement by Tata Steel UK Limited and Network Rail
Other
Size: 811 KB
Ben Lewis (Bilfinger GVA) on behalf of Tata Steel UK Limited
Statement of Common Ground between Tata Steel UK Limited and the City & County of Swansea
Other
Size: 66 KB
Section 99 Letter
Notification of completion of the examination
Documents can be filtered by the date they were published or by the deadline date that they relate to. Deadlines are publicised in the examination timetable at the beginning of the examination and can be viewed on the examination timetable tab.