Walney Extension Offshore Wind Farm

What happens next

A decision on the application for a Development Consent Order for Walney Extension Offshore Wind Farm was taken on 07 November 2014.

Timeline (10 items)

The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

29 January 2020
Decision made by the Secretary of State
07 November 2014
Recommendations given by the Planning Inspectorate
07 August 2014
  • Preliminary Meeting takes place
  • Examination begins
12 November 2013
Relevant representations published on the website
26 September 2013
Registration of interested parties closes
20 September 2013
Registration of interested parties begins
10 August 2013
Decision on whether or not to accept the application for examination
22 July 2013
  • Application expected from applicant
  • Application received by the Planning Inspectorate
28 June 2013