You can filter the results to show only the items that match your interest.
Documents Published By Stage
Pre Application (8)
Developer's Application (268)
Acceptance (23)
Pre Examination (448)
- All Documents
- Accompanied Site Inspection 1 (ASI1) (1)
- + Additional Submissions (314)
- Certificates and Notices (4)
- Examination Library (1)
- Hearing Agenda (1)
- Notification of the appointment of Examining Authority (1)
- Other Documents (1)
- Preliminary Meeting (12)
- Procedural Deadline A (47)
- Procedural Deadline B (32)
- Procedural Deadline C (18)
- Procedural Decisions (10)
- Relevant Representations Examination Library (1)
- Unaccompanied Site Inspection (5)
Examination (1334)
- All Documents
- Accompanied Site Inspection 4 (ASI4) (1)
- Accompanied Site Inspections 2 and 3 (ASI2 and ASI3) (1)
- Additional Submissions (23)
- Compulsory Acquisition Hearing 1 (CAH1) (5)
- Compulsory Acquisition Hearing 2 (CAH2) (6)
- Deadline 1 (D1) (68)
- Deadline 10 (D10) (86)
- Deadline 11 (D11) (32)
- + Deadline 2 (D2) (380)
- Deadline 3 (D3) (28)
- Deadline 3A (D3A) (70)
- Deadline 4 (D4) (156)
- Deadline 5 (D5) (107)
- Deadline 6 (D6) (85)
- Deadline 7 (D7) (126)
- Deadline 8 (D8) (73)
- Deadline 9 (D9) (11)
- Hearing Notice (3)
- Issue Specific Hearing 1 (ISH1) (9)
- Issue Specific Hearing 2 (ISH2) (10)
- Issue Specific Hearing 3 (ISH3) (10)
- Issue Specific Hearing 4 (ISH4) (15)
- Open Floor Hearing 1 (OFH1) (2)
- Open Floor Hearing 2 (OFH2) (2)
- Open Floor Hearings 1 and 2 (OFH1 and OFH2) (1)
- Preliminary meeting note (1)
- Procedural Decisions (16)
- Report on the Implications for European Sites (RIES) (1)
- Resumed Compulsory Acquisition Hearing 1 (CAH1) (5)
- Unaccompanied Site Inspection (1)
Decision (146)
Decided (0)
Source | Description |
---|---|
Other |
Relevant Representations Examination Library (PDF, 570 KB)
|
Other |
Preliminary Meeting - Day 2 - Session 1 - Transcript - 28 September 2022 (PDF, 86 KB)
This document is intended to assist Interested Parties, it is not verbatim. The content is produced using artificial intelligence voice to text and is unedited. The video recording remains as the primary record of the event.
|
Other |
Preliminary Meeting - Day 2 - Session 2 - Transcript - 28 September 2022 (PDF, 74 KB)
This document is intended to assist Interested Parties, it is not verbatim. The content is produced using artificial intelligence voice to text and is unedited. The video recording remains as the primary record of the event.
|
Other |
Preliminary Meeting - Day 2 - Session 3 - Transcript - 28 September 2022 (PDF, 46 KB)
This document is intended to assist Interested Parties, it is not verbatim. The content is produced using artificial intelligence voice to text and is unedited. The video recording remains as the primary record of the event.
|
Other | |
Other | |
Other | |
Other | |
Other |
Alan T Richardson (PDF, 62 KB)
Procedural Deadline C Submission
|
Other |
Anglian Water (PDF, 2 KB)
Procedural Deadline C Submission
|
Other |
Cambridgeshire County Council (PDF, 197 KB)
Procedural Deadline C Submission
|
Other |
Dr Edmund Fordham (PDF, 121 KB)
Procedural Deadline C Submission
|
Other |
East Cambridgeshire District Council (PDF, 120 KB)
Procedural Deadline C Submission
|
Other |
Royal Worlington and Newmarket Golf Club (PDF, 2 KB)
Procedural Deadline C Submission
|
Other |
Say No To Sunnica Action Group Ltd (PDF, 167 KB)
Procedural Deadline C Submission
|
Other |
Suffolk County Council (PDF, 130 KB)
Procedural Deadline C Submission
|
Other |
Sunnica Ltd (PDF, 221 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022 - FIGURE 3-28B SUNNICA WEST SITE A SUBSTATION GENERAL ARRANGEMENT - 400KV SOLUTION
|
Other |
Sunnica Ltd (PDF, 2 MB)
Procedural Deadline C Submission - Letter and draft itinerary for Accompanied Site Inspection 1
|
Other |
Sunnica Ltd (PDF, 226 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022 - FIGURE 3-30B SUNNICA EAST SITE B SUBSTATION GENERAL ARRANGEMENT - 400KV SOLUTION
|
Other |
Sunnica Ltd (PDF, 946 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022 - FIGURE 3-29A SUNNICA EAST SITE A SUBSTATION ELEVATION 400KV SOLUTION
|
Other |
Sunnica Ltd (PDF, 378 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022 - FIGURE 3-29B SUNNICA EAST SITE A SUBSTATION GENERAL ARRANGEMENT - 400KV SOLUTION
|
Other |
Sunnica Ltd (PDF, 421 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022 - FIGURE 3-28A SUNNICA WEST SITE A SUBSTATION ELEVATION - 400KV SOLUTION
|
Other |
Sunnica Ltd (PDF, 420 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022 - FIGURE 3-30A SUNNICA EAST SITE B SUBSTATION ELEVATION - 400KV SOLUTION
|
Other |
Sunnica Ltd (PDF, 254 KB)
Applicant's response to the Examining Authority's letter of 8 September 2022
|
Other |
The Ark Church Isleham (PDF, 215 KB)
Procedural Deadline C Submission
|
Other |
West Suffolk Council (PDF, 94 KB)
Procedural Deadline C Submission
|
Other | |
Other |
Examination Library (PDF, 113 KB)
Applicant's Change Request 30 August 2022
|
Other | |
Other |
Sunnica Ltd (PDF, 690 KB)
Applicant's Change Request 30 August 2022 - 6.2 Environmental Statement - Appendix 16C Framework Construction Environmental Management Plan
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Land and Crown Land Plan
|
Other |
Sunnica Ltd (PDF, 4 MB)
Applicant's Change Request 30 August 2022 - 2.4 Traffic Regulation Measures Plans - Road Closures Part 2 - Clean
|
Other |
Sunnica Ltd (PDF, 203 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix B - Schedule of Prescribed Consultees
|
Other |
Sunnica Ltd (PDF, 759 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-29 - Sunnica East Site A Elevation and General Arrangement - 400 kV Solution (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 10 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix Q - Framework Construction Traffic Management Plan and Travel Plan - Part 1
|
Other |
Sunnica Ltd (PDF, 704 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Nature Conservation, Habitats or Protected Species and Important Habitats Plan
|
Other |
Sunnica Ltd (PDF, 3 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Water Bodies in a River Basin Management Plan
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-20 Burwell Substation Extension Option 2 - Clean
|
Other |
Sunnica Ltd (PDF, 252 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix R - Letter to the Applicant from National Grid
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix K - Statement of Reasons - Tracked
|
Other |
Sunnica Ltd (PDF, 231 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix L - Schedule of Negotiations and Powers - Tracked
|
Other |
Sunnica Ltd (PDF, 10 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix A - Copy of Newspaper Notices and Letters
|
Other |
Sunnica Ltd (PDF, 948 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-28b - Sunnica West Site A Substation General Arrangement - 400 kV (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 967 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix H - Explanatory Memorandum - Tracked
|
Other |
Sunnica Ltd (PDF, 10 MB)
Applicant's Change Request 30 August 2022 - 2.3 Access and Rights of Way Plans - Clean
|
Other |
Sunnica Ltd (PDF, 83 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix C - Schedule of Local Authorities
|
Other |
Sunnica Ltd (PDF, 7 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix P - Abnormal Invisible Loads Required for Sunnica Energy Farm
|
Other |
Sunnica Ltd (PDF, 27 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-25 a to d - Cable Route Access Points - Tracked
|
Other |
Sunnica Ltd (PDF, 296 KB)
Applicant's Change Request 30 August 2022 - Cover Letter
|
Other |
Sunnica Ltd (PDF, 29 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix Q - Framework Construction Traffic Management Plan and Travel Plan - Part 2
|
Other |
Sunnica Ltd (PDF, 3 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix M - Copies of Consultation Responses Received
|
Other |
Sunnica Ltd (PDF, 28 MB)
Applicant's Change Request 30 August 2022 - 6.2 Environmental Statement - Appendix 13C Framework Construction Traffic Management and Travel Plan Part 2 (Clean)
|
Other |
Sunnica Ltd (PDF, 2 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix G - Draft Development Consent Order - Tracked
|
Other |
Sunnica Ltd (PDF, 6 MB)
Applicant's Change Request 30 August 2022 - 2.4 Traffic Regulation Measures Plans - Road Closures Part 1 - Clean
|
Other |
Sunnica Ltd (PDF, 161 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix D - Book of Reference Excerpts - Tracked
|
Other |
Sunnica Ltd (PDF, 217 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-30a Sunnica East Site B Substation Elevation 400kV Solution - Clean
|
Other |
Sunnica Ltd (PDF, 2 MB)
Applicant's Change Request 30 August 2022 - 4.1 Statement of Reasons - Clean
|
Other |
Sunnica Ltd (PDF, 30 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Location Plan
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Access and Rights of Way Plans
|
Other |
Sunnica Ltd (PDF, 1,009 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-28a - Sunnica West Site A Substation Elevation - 400 kV (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 29 MB)
Applicant's Change Request 30 August 2022 - 2.4 Traffic Regulation Measures Plan - Temporary Measures - Part 1 - Clean
|
Other |
Sunnica Ltd (PDF, 440 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix E - Chapter 0 - Table of Contents, Glossary and Abbreviations - Tracked
|
Other |
Sunnica Ltd (PDF, 807 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-30b - Sunnica East Site B Substation General Arrangement - 400 kV Solution (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 27 MB)
Applicant's Change Request 30 August 2022 - 2.4 Traffic Regulation Measures Plan - Temporary Measures - Part 2 - Clean
|
Other |
Sunnica Ltd (PDF, 8 MB)
Applicant's Change Request 30 August 2022 - 6.1 Environmental Statement - Chapter 3 Scheme Description - Clean
|
Other |
Sunnica Ltd (PDF, 504 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix O - Consultation Responses
|
Other |
Sunnica Ltd (PDF, 188 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-29 Sunnica East Site A Substation Elevation and GA 400kV Solution - Clean
|
Other |
Sunnica Ltd (PDF, 2 MB)
Applicant's Change Request 30 August 2022 - 8.2 Proposed Changes to the Application
|
Other |
Sunnica Ltd (PDF, 31 MB)
Applicant's Change Request 30 August 2022 - 6.2 Environmental Statement - Appendix 13C Framework Construction Traffic Management and Travel Plan Part 1 (Clean)
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 3.2 Explanatory Memorandum - Clean
|
Other |
Sunnica Ltd (PDF, 5 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix N - Consultation Document and Banners
|
Other |
Sunnica Ltd (PDF, 2 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Works Plans
|
Other |
Sunnica Ltd (PDF, 483 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-31 Cable Route Cross Sections 400kV Solution - Clean
|
Other |
Sunnica Ltd (PDF, 3 MB)
Applicant's Change Request 30 August 2022 - 2.4 Traffic Regulation Measures Plans - Road Closures Part 3 - Clean
|
Other |
Sunnica Ltd (PDF, 231 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-28b Sunnica West Site A Substation General Arrangement 400kV Solution - Clean
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-30a - Sunnica East Site B Substation Elevation - 400 kV Solution (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 11 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Traffic Regulation Measures Plan - Temporary Measures
|
Other |
Sunnica Ltd (PDF, 78 MB)
Applicant's Change Request 30 August 2022 - 7.3 Design and Access Statement - Clean
|
Other |
Sunnica Ltd (PDF, 210 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-28a Sunnica West Site A Substation Elevation 400kV solution - Clean
|
Other |
Sunnica Ltd (PDF, 781 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-20 - Option 2 Burwell National Grid Substation Extension - Tracked
|
Other |
Sunnica Ltd (PDF, 743 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix Q - Framework Construction Environmental Management Plan
|
Other |
Sunnica Ltd (PDF, 595 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-31 - Cable Route Cross Section - 400 kV Solution (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 3.1 Draft Development Consent Order (DCO) - Clean
|
Other |
Sunnica Ltd (PDF, 3 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix E - Chapter 3 - Scheme Description - Tracked
|
Other |
Sunnica Ltd (PDF, 30 MB)
Applicant's Change Request 30 August 2022 - 2.7 Water Bodies in a River Basin Management Plan - Clean
|
Other |
Sunnica Ltd (PDF, 196 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-30b Sunnica East Site B Substation General Arrangement 400kV Solution - Clean
|
Other |
Sunnica Ltd (PDF, 7 MB)
Applicant's Change Request 30 August 2022 - 2.8 Features of the Historic Environment Plan - Clean
|
Other |
Sunnica Ltd (PDF, 11 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix F - Design and Access Statement - Tracked
|
Other |
Sunnica Ltd (PDF, 16 MB)
Applicant's Change Request 30 August 2022 - 2.2 Work Plans - Clean
|
Other |
Sunnica Ltd (PDF, 511 KB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Features of the Historic Environment Plan
|
Other |
Sunnica Ltd (PDF, 14 MB)
Applicant's Change Request 30 August 2022 - 2.6 Statutory and Non-Statutory Sites or Features of Nature Conservation, Habitats of Protected Species and Important Habitats Plan - Clean
|
Other |
Sunnica Ltd (PDF, 10 MB)
Applicant's Change Request 30 August 2022 - 2.5 Location Plan - Clean
|
Other |
Sunnica Ltd (PDF, 15 MB)
Applicant's Change Request 30 August 2022 - 2.1 Land and Crown Land Plans - Clean
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix J - Figure 3-32 - Joint Bay Sections - 400 kV Solution (Illustrative) - Tracked
|
Other |
Sunnica Ltd (PDF, 8 MB)
Applicant's Change Request 30 August 2022 - 8.2 Appendix I - Volume 2 - Traffic Regulation Measures - Road Closure
|
Other |
Sunnica Ltd (PDF, 395 KB)
Applicant's Change Request 30 August 2022 - 6.1 Environmental Statement - Table of Contents, Glossary and Abbreviations - Clean
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-25 a to d Cable Route Access Points - Clean
|
Other |
Sunnica Ltd (PDF, 3 MB)
Applicant's Change Request 30 August 2022 - 4.3 Book of Reference - Clean
|
Other |
Sunnica Ltd (PDF, 754 KB)
Applicant's Change Request 30 August 2022 - 6.3 Environmental Statement Figure 3-32 Joint Bay Sections 400kV Solution - Clean
|
Other |
Sunnica Ltd (PDF, 1 MB)
Applicant's Change Request 30 August 2022 - 4.4 Schedule of Negotiations and Powers Sought - Clean
|
Other | |
Other |
Anne Noble (PDF, 57 KB)
Procedural Deadline B - Response to Examining Authority's letter of 28 July 2022
|
Other |
Anne Noble (PDF, 63 KB)
Procedural Deadline B Submission
|
Other |
Alan Smith (PDF, 155 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Alan Smith (PDF, 49 KB)
Procedural Deadline B Submission
|
Other |
Angela Wells (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Annette Flindall (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Brenda Knowles (PDF, 3 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Brian Challis (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Cambridgeshire County Council (PDF, 188 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Catherine Judkins (PDF, 3 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Chippenham Parish Council (PDF, 515 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Claudine Bateman (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Colin Day (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
D R Kerr (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Dale Hing (PDF, 48 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Dale Hing (PDF, 76 KB)
Procedural Deadline B Submission
|
Other |
East Cambridgeshire District Council (PDF, 106 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Isabel Cross (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Justin Fuga (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Louise Skole Andreasen (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Tattersalls Ltd on behalf of Newmarket Horseman's Group (PDF, 82 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Nick Wright (PDF, 487 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Nicole Langstaff (PDF, 76 KB)
Procedural Deadline B Submission
|
Other |
Nicole Langstaff (PDF, 70 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other | |
Other | |
Other |
Olivia Pitts (PDF, 1 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Peter Knowles (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Roy Clarke (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Say No To Sunnica Action Group Ltd (PDF, 2 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Say No To Sunnica Action Group Ltd (PDF, 2 KB)
Procedural Deadline B Submission
|
Other |
Suffolk County Council (PDF, 165 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
Sunnica Ltd (PDF, 127 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other |
West Suffolk Council (PDF, 80 KB)
Procedural Deadline B Submission - Response to the Examining Authority's letter of 28 July 2022
|
Other | |
Other | |
Other | |
Other | |
Other |
Transcript of Part 1 of the Preliminary Meeting Tuesday 26 July 2022 (PDF, 188 KB)
This document is intended to assist Interested Parties, it is not verbatim. The content is produced using artificial intelligence voice to text and is unedited. The video recording remains as the primary record of the event.
|
Other |
Transcript of Part 2 of the Preliminary Meeting Tuesday 26 July 2022 (PDF, 106 KB)
This document is intended to assist Interested Parties, it is not verbatim. The content is produced using artificial intelligence voice to text and is unedited. The video recording remains as the primary record of the event.
|
Other |
Transcript of Part 3 of the Preliminary Meeting Tuesday 26 July 2022 (PDF, 109 KB)
This document is intended to assist Interested Parties, it is not verbatim. The content is produced using artificial intelligence voice to text and is unedited. The video recording remains as the primary record of the event.
|
Other | |
Other |
Eversheds Sutherland (International) LLP on behalf of National Grid Gas Plc and National Grid Electricity Transmission Plc (PDF, 112 KB)
Additional Submission – Correspondence regarding Preliminary Meeting – Accepted at the discretion of the Examining Authority
|
Other |
Alan Richardson (PDF, 42 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Anne Noble (PDF, 39 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Antony and Margaret Cornell (PDF, 40 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Bryan Cave Leighton Paisner LLP on behalf of HPUT A Limited and HPUT B Limited (PDF, 145 KB)
Additional Submission – Letter in lieu of attendance at the Preliminary Meeting – Accepted at the discretion of the Examining Authority
|
Other |
Linda Homan (PDF, 46 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other | |
Other |
Sunnica Ltd (PDF, 2 MB)
Additional Submission - Letter from the Applicant regarding notification of hearings - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 1 MB)
Additional Submission - Letter from the Applicant proposing timetable amendments - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 178 KB)
Additional Submission - Letter from the Applicant regarding changes to the application - Accepted at the discretion of the Examining Authority
|
Other |
West Suffolk Council (PDF, 114 KB)
Procedural Deadline A Submission
|
Other | |
Other |
Nick Wright (PDF, 96 KB)
Additional Submission accepted at the discretion of the Examining Authority
|
Other |
Alan Smith (PDF, 49 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Andrew Munro (PDF, 3 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Brenda Knowles (PDF, 5 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Cambridgeshire and Peterborough Combined Authority (PDF, 2 KB)
Procedural Deadline A Submission - Initial Assessment of Principle Issues
|
Other |
Cambridgeshire and Peterborough Combined Authority (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Cambridgeshire County Council (PDF, 206 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Catherine Judkins (PDF, 94 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined, including suggested locations for site inspection
|
Other |
Chippenham Parish Council (PDF, 4 MB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Chris Davison (PDF, 1 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Dale Hing (PDF, 154 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined, including suggested locations for site inspection
|
Other |
Dr Edmund Fordham (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Dr Edmund Fordham (PDF, 2 KB)
Procedural Deadline A Submission - Suggested locations for site inspection
|
Other |
Dr Edmund Fordham (PDF, 3 KB)
Procedural Deadline A Submission
|
Other |
Dr Edmund Fordham (PDF, 2 KB)
Procedural Deadline A Submission
|
Other |
East Cambridgeshire District Council (PDF, 173 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Peter Goodyear on behalf of Fordham (Cambs) Walking Group (PDF, 3 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Fordham Parish Council (PDF, 4 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing
|
Other |
Isabel Cross (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Isleham Parish Council (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Isleham Parish Council (PDF, 103 KB)
Procedural Deadline A Submission
|
Other |
Josie Jennings (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Justin Fuga (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Lucy Frazer MP and Matt Hancock MP (PDF, 5 MB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Mehreen Qayum-Millard (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Mark Knight on behalf of Mildenhall High Town Council (PDF, 1 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Eversheds Sutherland (International) LLP on behalf of National Grid Electricity Transmission Plc (PDF, 46 KB)
Procedural Deadline A Submission - Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; comments on compulsory acquisition and the draft Development Consent Order
|
Other |
Eversheds Sutherland (International) LLP on behalf of National Grid Gas Plc (PDF, 45 KB)
Procedural Deadline A Submission - Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; comments on compulsory acquisition and the draft Development Consent Order
|
Other |
Nick Wright (PDF, 5 MB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Nicole Langstaff (PDF, 154 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined, including suggested locations for site inspection
|
Other |
Peter Knowles (PDF, 2 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined, including suggested locations for site inspection
|
Other |
Peter Maxwell (PDF, 162 KB)
Procedural Deadline A Submissions - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing
|
Other |
Reach Parish Council (PDF, 89 KB)
Procedural Deadline A Submission
|
Other |
Red Lodge Parish Council (PDF, 190 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Roy Clarke (PDF, 9 KB)
Procedural Deadline A Submission - Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing
|
Other |
Sandie Geddes (PDF, 1 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined
|
Other |
Sandie Geddes (PDF, 3 KB)
Procedural Deadline A Submission - Suggested locations for site inspection and visualisations
|
Other |
Say No To Sunnica Action Group Ltd (PDF, 3 MB)
Procedural Deadline A Submission - Written submission about how the application should be examined, including suggested locations for site inspection
|
Other |
Snailwell Parish Council (PDF, 55 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Suffolk County Council (PDF, 426 KB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Sunnica Ltd (PDF, 3 MB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other |
Sunnica Ltd (PDF, 36 MB)
Procedural Deadline A Submission - Annex 3 - 6.2 Appendix 7H: Sunnica East Sites A and B Archaeological Trial Trenching Report
|
Other |
Worlington Parish Council (PDF, 1 MB)
Procedural Deadline A Submission - Written submission about how the application should be examined; Request to participate at the Preliminary Meeting, Issue Specific Hearing or Open Floor Hearing; Suggested locations for site inspection
|
Other | |
Other |
Sunnica Ltd (PDF, 124 KB)
Additional Submission accepted at the discretion of the Examining Authority - Applicants notice of public exhibitions relating to the ongoing consultation
|
Other |
Sunnica Ltd (PDF, 98 KB)
Additional Submission accepted at the discretion of the Examining Authority - Applicants Notice publicising Consultation on proposed changes to the application
|
Other |
Examination Library (PDF, 151 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other | |
Other |
Sunnica Ltd (PDF, 450 KB)
Additional Submission – Further response (20 and 24 May 2022) to Examining Authority’s letter dated 22 April 2022 - Method Statement consultation on proposed changes to DCO application
|
Other |
AG Wright and Son (Farms) Ltd (PDF, 132 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Alan Borderick (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Alan Smith (PDF, 222 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Alan Waterfield (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Alastair Game (PDF, 96 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Alexander Wright (PDF, 82 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Alexandra Hunt (PDF, 91 KB)
Response to the Examing Authority's letter dated 4 May 2022
|
Other |
André Ciantar (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Andrew and Nicola Farr (PDF, 123 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Andrew Beardon (PDF, 178 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Andrew Boyce (PDF, 88 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Andrew Geddes (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Andrew Levell (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party accepted at the discretion of the Examining Authority
|
Other |
Andrew Mackenzie (PDF, 123 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Andrew Munro (PDF, 84 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Angela Bishop (PDF, 83 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Anne Lister (PDF, 89 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Anne Noble (PDF, 108 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Anthony Bowser (PDF, 114 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Anthony Speed (PDF, 79 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Archie Bannister (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Archie Wright (PDF, 113 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Barbara Murfitt (PDF, 97 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Benoit Herinckx (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Brenda Knowles (PDF, 180 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Brian Challis (PDF, 87 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Cambridgeshire & Peterborough Combined Authority (PDF, 431 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Cambridgeshire County Council, East Cambridgeshire District Council, Suffolk County Council and West Suffolk Council (PDF, 454 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Cecelia Hawley (PDF, 125 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Celia Clarke (PDF, 113 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Chippenham Parish Council (PDF, 243 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Chris Davison (PDF, 96 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Chris Hall & Michelle Ferris (PDF, 99 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Chris Royston (PDF, 126 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Christopher Corbin (PDF, 162 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Claire Mills (PDF, 129 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Colin Lister (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Colleen Alexander (PDF, 99 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Coral Fuller (PDF, 96 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Daisy Ussher (PDF, 105 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Dale Hing (PDF, 101 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Deirdre Hyde (PDF, 95 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Denis Field (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Donald MacBean (PDF, 107 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Douglas Longmuir (PDF, 113 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Dr Catherine Judkins (PDF, 152 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Dr John Bruton (PDF, 83 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Ed Lubbock (PDF, 110 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Elaine Roe (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Elizabeth Garget (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Elizabeth Klingaman (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Ellen Clowes (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Emma Ryan (PDF, 2 MB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Evelyn Muldoon (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other | |
Other |
Terry Wood on behalf of Exning Parish Council (PDF, 78 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Fergus McCoig (PDF, 95 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Fergus Wright (PDF, 185 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Fiona Maxwell (PDF, 87 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Fiona McIntyre (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Fiona Peachey (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Francesca Muldoon (PDF, 131 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Freckenham Parish Council (PDF, 133 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Gary Tucker (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Geoff Mitchell (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
George Gordon Rusk (PDF, 148 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
George Moss (PDF, 155 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Geraldine Ciantar (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Godolphin Management Company Limited (PDF, 218 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Hampton Heritage Design and Consultancy Ltd (PDF, 83 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party submitted at the discretion of the Examining Authority
|
Other |
Hazel N Fleet (PDF, 114 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Health & Safety Executive (PDF, 325 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Heather Tilbrook (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Helen Faulkner (PDF, 117 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Helen Palmer (PDF, 87 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Henrietta Deasy (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Historic England (PDF, 46 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Ian Garget (PDF, 111 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Isabel Cross (PDF, 128 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Isleham Nature Reserves (PDF, 66 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Isleham Parish Council (PDF, 128 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Isobel Newport-Mangell (PDF, 142 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jack Smith (PDF, 238 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jacqueline Burke (PDF, 117 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jan Stewart (PDF, 268 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jane Grant (PDF, 88 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jean Mullin (PDF, 116 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jeanette Borderick (PDF, 118 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jennifer Hall (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jenny White (PDF, 222 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jeremy Richardson (PDF, 112 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jessica Wright (PDF, 113 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jill Worth (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Joanna Reeks (PDF, 107 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jockey Club Estates (PDF, 72 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John A Leitch (PDF, 107 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John Bavister (PDF, 103 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John Bridges (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John Carrington (PDF, 85 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John Derry (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
John Dimmock (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John Gosden Ltd (PDF, 4 MB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John James (PDF, 99 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
John Reali (PDF, 85 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Jonathan Pearce (PDF, 99 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Joseph Pattison (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Josie Jennings (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Judi Thurlow (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Justin Fuga (PDF, 96 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Karen Robinson (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Katherine Stewart (PDF, 76 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Kay Blackwell (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Kennett Parish Council (PDF, 127 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Kevin Hempson (PDF, 96 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Kevin Pallant (PDF, 84 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Kieran Coffey (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Lesley Wilson (PDF, 107 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Liam and Clare MacGillivray (PDF, 98 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Linda and Daryl Trundley (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Linda Breeze (PDF, 98 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Linda Homan (PDF, 128 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Linda Porter-Cohen (PDF, 76 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Lisa Bowman (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Louise Andreasen (PDF, 82 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Lucinda Wright (PDF, 116 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Lucy Frazer MP and Matt Hancock MP (PDF, 4 MB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Margaret Cornell (PDF, 85 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Marianne Corbin (PDF, 122 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Marie Beaumont (PDF, 82 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mark Caswell (PDF, 83 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mark Homan (PDF, 100 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Martin Attree (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Martin Swaffer (PDF, 87 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mehreen Qayum Millard (PDF, 89 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Michael Cullen (PDF, 89 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Michael Spooner (PDF, 61 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Michael Wallis (PDF, 33 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
MOD Defence Infrastructure Organisation (PDF, 263 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Moira Newell (PDF, 138 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Moira Newell (PDF, 115 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Morgan Sport (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mr & Mrs M S P Stone (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mr and Mrs L.J. Wightman (PDF, 66 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mr S C Hall (PDF, 120 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mrs Delyse Ray (PDF, 110 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mrs Olivia Pitts (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mrs S A Hall (PDF, 119 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Mrs Sam Lee-McCloud (PDF, 90 KB)
Late Response to the Examining Authority's letter dated 4 May 2022 - Accepted at the discretion of the Examining Authority
|
Other |
Mrs Sandra Judkins (PDF, 91 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
National Grid Electricity Transmission Plc (PDF, 67 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Netty Flindall (PDF, 69 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Newmarket Town Council (PDF, 444 KB)
Late Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Accepted at the discretion of the Examining Authority
|
Other |
Nick and Wendy Parsons (PDF, 92 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Nick Bennett (PDF, 170 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Nick Wright (PDF, 102 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Nicole Langstaff (PDF, 100 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Nigel Cooper (PDF, 142 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Nikki Lushington (PDF, 144 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Norman Ferguson (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Norman Ferguson (PDF, 88 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other | |
Other | |
Other |
Parish and Town Council Alliance (PDF, 103 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Parochial Church Council (PDF, 160 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Paul Fishpool (PDF, 190 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Paul Mangell (PDF, 104 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Paul Ryan (PDF, 85 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Paula MacKenzie (PDF, 171 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Peter Alder (PDF, 102 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Peter Knowles (PDF, 84 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Peter Maxwell (PDF, 158 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Peter Moggridge (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Philip Davis (PDF, 81 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Phyllis Rusk (PDF, 117 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
R F Turner & Son (PDF, 2 MB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Rachel Hood (PDF, 169 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Rebecca Norbury (PDF, 124 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Red Lodge Parish Council (PDF, 163 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Richard and Tracey Minshull (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Richard Furlonger (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Richard Liddington (PDF, 83 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Richard Payne (PDF, 186 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Richard Radcliffe (PDF, 94 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Robert Savage (PDF, 107 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Robin Grant (PDF, 44 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Roger Osborn (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Rosalind Hamill (PDF, 88 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Royal Worlington & Newmarket Golf Club (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Rupert Osborn (PDF, 115 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
S Shujah (PDF, 88 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
S Trett (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sally Hempson (PDF, 95 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Samantha Munro (PDF, 89 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sandie Geddes (PDF, 105 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sandra Desborough (PDF, 90 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sandra Dwan (PDF, 91 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sara Beckett (PDF, 87 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sara Caswell (PDF, 110 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sarah Ganiford (PDF, 93 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Say No To Sunnica Action Group Ltd (PDF, 620 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sean McGinty (PDF, 155 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Sean Newell (PDF, 77 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Simon Stafford (PDF, 227 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Snailwell Parish Council (PDF, 252 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Solar Compaign Alliance - SCA (PDF, 246 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Stephen Wilson (PDF, 111 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Steve Gladwin (PDF, 190 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Susan Derry (PDF, 119 KB)
Response to the Examining Authority's letter dated 4 May 2022 - Non-Interested Party Submission accepted at the discretion of the Examining Authority
|
Other |
Suzanne Royston (PDF, 127 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Tattersalls Ltd (PDF, 3 MB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Teresa Peachey (PDF, 86 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
The Ark Church Isleham (PDF, 85 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Tim Lawson (PDF, 110 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Trevor Layn (PDF, 121 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other |
Worlington Parish Council (PDF, 154 KB)
Response to the Examining Authority's letter dated 4 May 2022
|
Other | |
Other |
Sunnica Ltd (PDF, 303 KB)
Additional Submission - Response to the Examining Authority's letter dated 22 April 2022
|
Other |
RESCUE, The British Archaeological Trust (PDF, 288 KB)
Additional Submission - Non-IP - Accepted at the discretion of the Examining Authority
|
Other | |
Other | |
Other |
Sunnica Ltd (PDF, 84 KB)
Additional Submission – Request by the Applicant (19 April 2022) in respect of the timing of the Preliminary Meeting/Examination – Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 88 KB)
Additional Submission – Request by the Applicant (30 March 2022) in respect of the timing of the Preliminary Meeting/Examination – Accepted at the discretion of the Examining Authority
|
Other |
East of England Ambulance Service NHS Trust (PDF, 721 KB)
Additional Submission - Accepted at the discretion of the Examining Authority
|
Other |
National Highways (PDF, 75 KB)
Additional Submission - Accepted at the discretion of the Examining Authority
|
Other |
NATS Ltd, Safeguarding Office (PDF, 90 KB)
Additional Submission - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 909 KB)
Section 56 Compliance Certificate
|
Other |
Sunnica Ltd (PDF, 76 KB)
Certificate of compliance with section 59
|
Other |
Sunnica Ltd (PDF, 24 KB)
Certificate of compliance with regulation 16
|
Other |
The Coal Authority (PDF, 170 KB)
Additional Submission - Accepted at the discretion of the Examining Authority
|
Other | |
Other |
Sunnica Ltd (PDF, 133 KB)
Section 56 Notice
|
Other |
Sunnica Ltd (PDF, 11 MB)
Applicant's response to s51 advice - 6.2 Appendix 9C - Flood Risk Assessment - Part 1 - Tracked - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 27 MB)
Applicant’s response to s51 advice - 2.1 Land and Crown Plans - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 14 MB)
Applicant’s response to s51 advice - 2.2 Works Plans - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 90 MB)
Applicant’s response to s51 advice - 6.2 Appendix 9C - Flood Risk Assessment - Part 2 - Rev 1 -Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 3 MB)
Applicant’s response to s51 advice - 6.2 Appendix 9C - Flood Risk Assessment - Part 3 - Rev 1 -Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 10 MB)
Applicant’s response to s51 advice - 2.5 Location Plan - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 154 KB)
Applicant’s response to s51 advice - Cover Letter - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 16 MB)
Applicant’s response to s51 advice - 6.2 Appendix 9C - Flood Risk Assessment - Part 4 - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 13 MB)
Applicant’s response to s51 advice - 6.2 Appendix 9C - Flood Risk Assessment - Part 1 - Rev 1 -Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 2 MB)
Applicant’s response to s51 advice - 1.2 Guide to the Application - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 11 MB)
Applicant’s response to s51 advice - 6.3 Figure 9-1 - Surface Water Bodies and their Attributes - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Sunnica Ltd (PDF, 10 MB)
Applicant’s response to s51 advice - 2.3 Access and Rights of Way - Rev 1 - Accepted at the discretion of the Examining Authority
|
Other |
Examination Library (PDF, 1 MB)
|