Hornsea Project Three Offshore Wind Farm

Received 25 June 2018
From Kelling Parish Council

Representation

We are concerned that not enough has been done to reduce the problem of construction traffic and speeding in the village of Kelling.

We do not understand why Pudding Lane,Kelling, which is a restricted byway and well used footpath, should be temporary closed where it meets the A149 coast road during construction. This is at the edge of the construction area, and it is easily possible to move the area over to the west by only 10 metres, and widen the access gateway to the field to allow larger vehicle entry / egress. This would allow Pudding Lane to remain open at all times and allow uninterrupted access to Pudding Lane Cottage.