East Anglia TWO Offshore Windfarm

This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.

May 2021

MondayTuesdayWednesdayThursdayFridaySaturdaySunday
1
2
3
4
5
6

7
8
9
10
11
12
13
14
15
16
17
18
19
20

21
22
23
24
25
26

27
28

29
30
31

Details: Deadline 10 Deadline for receipt by ExA of: • Comments on any supplementary information received by D9 • Comments on any additional information/submissions received at D9 • Responses to any further information requested by the ExAs for this deadline

Start Time: 23:59:00

Details: Publication by ExA of: • ExA’s commentary on and/or schedule of changes to the dDCO (if required) • ExA’s Further Written Questions (ExQ3)

Start Time: 23:59:00

Details: ISH16 Proposed substations site

Start Time: 10:00:00

Details: ISH17 draft Development Consent Order (dDCO)

Start Time: 10:00:00