Knottingley Power Project

What happens next

A decision on the application for a Development Consent Order for Knottingley Power Project was taken on 10 March 2015.

Timeline (10 items)

The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

12 June 2020
Decision made by the Secretary of State
10 March 2015
Recommendations given by the Planning Inspectorate
12 December 2014
  • Preliminary Meeting takes place
  • Examination begins
13 March 2014
Relevant representations published on the website
30 January 2014
Registration of interested parties closes
06 January 2014
Registration of interested parties begins
14 November 2013
Decision on whether or not to accept the application for examination
31 October 2013
Application received by the Planning Inspectorate
04 October 2013