Hornsea Offshore Wind Farm (Zone 4) – Project Two

You can filter the results to show only the items that match your interest.

Documents Published By Stage

Pre Application (8)

Developer's Application (213)

Acceptance (12)

Pre Examination (15)

Examination (447)

Decision (65)

Decided (35)

Date

The filtered list shows documents relating to the decision for the development consent order.

SourceDescription
Other
Size: 67 KB
The Crown Estate
Correspondence between The Crown Estate and the Department for Business, Energy and Industrial Strategy
Other
Size: 4 MB
Habitats Regulation Assessment
Other
Size: 110 KB
Notice of the Decision by the Secretary of State (Reg 23)
Other
Other
Size: 40 KB
Post Examination Correspondence Log
Other
Size: 4 MB
Hornsea Project 2 - Recommendation Report
Other
Size: 1 MB
Development Consent Order made by the Secretary of State
Other
Size: 819 KB
Northern Power Grid
Correspondence received following the Close of Examination
Other
Size: 900 KB
E.ON E&P UK Limited
Correspondence received following the Close of Examination
Other
Size: 95 KB
Submission from Dong- Hornsea Project 2 and The Wildlife Trust
Correspondence sent to the Secretary of State
Other
Size: 48 KB
Whale and Dolphin Conservation
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 374 KB
The Wildlife Trust
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 185 KB
Belgium- Department of European policies and international agreements
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 146 KB
Natural England
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 844 KB
Dong- Hornsea Project 2
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 251 KB
Defense Infrastructure Organisation
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 126 KB
The Crown Estate
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 434 KB
Royal Society for the Protection of Birds
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 49 KB
Scottish Natural Heritage
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 150 KB
Marine Management Organisation
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 209 KB
Natural England and the Joint Nature Conservation Committee
Response to Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 214 KB
Department of Energy and Climate Change- Request for Comments Issued 12 July 2016
Other
Size: 56 KB
Peterborough City Council
Late response to DECC Consultation request issued 8 June 2016
Other
Size: 54 KB
Quadrant Pipelines Limited, Independent Pipelines Limited and GTC Pipelines Limited
Response to Request for Comments
Other
Size: 220 KB
Natural England and the Joint Nature Conservation Committee
A joint response from Natural England and the Joint Nature Conservation Committee on the Applicant’s Harbour Porpoise information submitted on 24th May 2016
Other
Size: 16 KB
Anglian Water
Response to Request for Comments
Other
Size: 16 KB
Anglian Water
Response to Request for Comments
Other
Size: 189 KB
Natural England
Response to the questions regarding Fulmar displacement.
Other
Size: 2 MB
The Wildlife Trusts
Further response to Request for Comments
Other
Size: 489 KB
Royal Society for the Protection of Birds
Response to Request for Comments
Other
Size: 796 KB
The Wildlife Trusts
Response to Request for Comments
Other
Size: 52 KB
Whale and Dolphin Conservation
Response to Request for Comments
Other
Size: 162 KB
Marine Management Organisation
Response to Request for Comments
Other
Size: 536 KB
Dong - Hornsea Project 2
Regarding Topic 2 : Fulmar Displacement Mortality.
Other
Size: 218 KB
Hornsea Project 2 - Further Extension to Department of Energy and Climate Change consultation deadline
Letter from the Department of Energy and Climate Change regarding a further extension to the deadline for responses to the consultation request.
Other
Size: 127 KB
DECC consultation letter Hornsea Offshore Windfarm (Zone 4) -Project
Letter from the Department of Energy and Climate Change - Request for comments on the application.
Other
Size: 197 KB
Hornsea Two Letter from Secretary of State regarding an Extension
Letter from the Department of Energy and Climate Change regarding an Extension to the deadline for the decision on the application
Other
Size: 442 KB
Dong - Hornsea Project 2
Response to the Department of Energy and Climate Change consultation commenting on submissions made by other interested parties on 13 May 2016.
Other
Size: 341 KB
Royal Society for the Protection of Birds
Response to consultation undertaken by the Department of Energy and Climate Change on 28 April 2016
Other
Size: 594 KB
The Wildlife Trusts
Response to consultation undertaken by the Department of Energy and Climate Change on 28 April 2016
Other
Size: 49 KB
Whale and Dolphin conservation
Response to consultation undertaken by the Department of Energy and Climate Change on 28 April 2016
Other
Size: 242 KB
Joint Nature Conservation Bodies and Natural England
Response to consultation undertaken by the Department of Energy and Climate Change on 28 April 2016
Other
Size: 103 KB
Other
Size: 47 KB
Department for Energy and Climate Change - Extension to deadline
Letter confirming an extension to the deadline for responses to the letter issued 28 April 2016. The deadline has now been extended to Friday 13 May 2016.
Other
Size: 44 KB
Department of Energy and Climate Change Consultation Letter Dated 28 April 2016
Invitation by the Secretary of State for Energy and Climate Change for comments from Natural England, the Joint Nature Conservation Committee and any other Interested Party on the Applicant?s submission of 21 April 2016
Other
Size: 341 KB
Dong- Hornsea Project 2
Appendix B - Response to Q2 - Ornithology. Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 2 MB
Dong - Hornsea Project 2
Appendix C - Submissions from North Lincolnshire Council and Historic England in response to Q3. Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 884 KB
Dong - Hornsea Project 2
Appendix D - Letter of Withdrawal from Northern Powergrid (Yorkshire) plc. Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 2 MB
Dong-Hornsea Project 2
Appendix A - Response to Q1 - Harbour Porpoise. Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 427 KB
Dong - Hornsea Project 2
The Applicant's response to Request for Comments from the Secretary of State - 21 April 2016. Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 137 KB
Historic England
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 127 KB
Anglian Water
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 196 KB
E.ON E&P UK Limited
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 435 KB
RSPB
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 330 KB
North Lincolnshire Council
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 193 KB
West Lindsey District Council
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 139 KB
The Wildlife Trusts
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 149 KB
Natural England
Response to consultation undertaken by the Department of Energy and Climate Change on 7 April 2016
Other
Size: 54 KB
Department for Energy and Climate Change consultation letter dated 7 April 2016
Other
Size: 161 KB
Joint Nature Conservation Bodies and Natural England
Response to consultation undertaken by the Department of Energy and Climate Change on 29 March 2016.
Other
Other
Size: 1 MB
Examination Library
Other
Size: 66 KB
Notification of Completion of ExA Examination
Other
Size: 150 KB
E.ON E&P UK Ltd
Response to the Applicant's Deadline 8 submission. Accepted at the discretion of the Examining Authority.
Other
Size: 496 KB
Royal Society for the Protection of Birds
Response to Deadline 8 Submissions from interested parties. Accepted at the discretion of the Examining Authority.
Documents can be filtered by the date they were published or by the deadline date that they relate to. Deadlines are publicised in the examination timetable at the beginning of the examination and can be viewed on the examination timetable tab.