Drax Re-power

What happens next

04/10/2019 - Deadline for Secretary of State to make decision

The Examining Authority issued a Recommendation Report to the Secretary of State on 04 July 2019. The Secretary of State has three months in which to issue a decision. The decision letter and Recommendation Report will be published on this project page once a decision has been made.

Timeline (38 items)

milestone icon
Recommendations given by the Planning Inspectorate
04 July 2019
notice icon

The deadline for close of examination is midnight 4 April 2019.

04 April 2019
notice icon

The Submissions for Deadline 9 have now been published.

29 March 2019
notice icon

The Submissions for Deadline 8 have now been published.

22 March 2019
notice icon

The Submissions for Deadline 7 have now been published.

21 February 2019
notice icon

The Action Points from Issue Specific Hearing 3 have now been published.

20 February 2019
notice icon

The Audio recordings for Compulsory Acquisition Hearing 2, Open Floor Hearing 3, and Issue Specific Hearing 3 have now been published.

13 February 2019
notice icon

The agenda for Issue Specific Hearing 2 (ISH2) has now been published.

06 February 2019
notice icon

The Deadline 6 Submissions have now been published.

06 February 2019
notice icon

A procedural decision has been issued relating to the Applicant’s proposed changes to the application.

The Notification letter for the hearings taking place on the 12 of February 2019 has been published.

The Examination Authority’s Further Written Questions have also been published.

15 January 2019
notice icon

The Deadline 5 Submissions have now been published.

10 January 2019
notice icon

The documents for deadline 4 have now been published.

14 December 2018
notice icon

The Examining Authority has issued a procedural decision regarding an application for additional land.

The Examining Authority has issued a procedural decision regarding the Site Reconfiguration Works and a request for further information.

An additional submission (Letter from North Yorkshire County Council) has been accepted at the discretion of the Examining Authority.

03 December 2018
notice icon

An additional submission (6.2.9.10 Appendix 9.10 – Biodiversity Net Gain Assessment – Appendix 3 – Maps) has been accepted at the discretion of the Examining Authority.

 

19 November 2018
notice icon

The preliminary meeting note and the submissions for deadline 2 have been published.

12 November 2018
notice icon

The notification letter for the Accompanied Site Inspection (4 December 2018) and  Hearings (4 December 2018 – 6 December 2018) has been published.

06 November 2018
notice icon

The submissions for deadline 1 have now been published.

19 October 2018
milestone icon Read the letter

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties

Procedural decision following Preliminary Meeting

11 October 2018
milestone icon
  • Preliminary Meeting takes place
  • Examination begins
04 October 2018
notice icon

The agenda for the forthcoming open floor hearing has been published.

24 September 2018
notice icon
11 September 2018
milestone icon

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

06 September 2018
milestone icon
Relevant representations published on the website
04 September 2018
milestone icon
Registration of interested parties closes
29 August 2018
milestone icon
Registration of interested parties begins
20 July 2018
milestone icon Read the letter

The application has been accepted for examination

26 June 2018
milestone icon
Decision on whether or not to accept the application for examination
26 June 2018
milestone icon
Application received by the Planning Inspectorate
29 May 2018