Drax Re-power

You can filter the results to show only the items that match your interest.

Date

SourceDescription
Other
Size: 169 kB
Ouse & Humber Drainage Board
The Ouse & Humber Drainage Board were omitted from the scoping consultation due to a technical error by the Planning Inspectorate. They were notified of the Proposed Development on 8 February 2018 and submitted this response on 12 February 2018.
Other
Size: 403 kB
Ouse & Derwent Internal Drainage Board
The Ouse & Derwent Internal Drainage Board were omitted from the scoping consultation due to a technical error by the Planning Inspectorate. They were notified of the Proposed Development on 8 February 2018 and submitted this response on 12 February 2018.
Other
Size: 257 kB
Drax Power Limited
S46 Notification
Other
Size: 79 kB
Acknowledgement of S46 Notification
Other
Size: 15 MB
Late Scoping Consultation Responses
Late Scoping Consultation Responses for Drax Repower Project. Published on 23 October 2017.
Other
Size: 4 MB
Scoping Opinion
Scoping Opinion for Drax Repower Project adopted by the Secretary of State on 23 October 2017.
Other
Size: 4 MB
Scoping Report
The Applicant's Scoping Report for Drax Repower Project. Submitted to the Secretary of State on 14 September 2017.
Documents can be filtered by the date they were published or by the deadline date that they relate to. Deadlines are publicised in the examination timetable at the beginning of the examination and can be viewed on the examination timetable tab.