Abergelli Power

This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.

Event DateDescription
 Date Passed
10 October 2018
Issue Specific Hearing 1
ISH1 into:
• the draft Development Consent Order (dDCO)
 Date Passed
11 October 2018
Examination Begins
 Date Passed
17 October 2018
Issue by the ExA of
• Examination Timetable (including the date for any hearings);
• The ExA’s First Written Questions (ExQs).
 Date Passed
09 November 2018
Deadline for receipt by the ExA of:
• Comments on Relevant Representations (RRs);
• Summaries of all RRs exceeding 1500 words;
• Written Representations (WRs);
• Summaries of all WRs exceeding 1500 words;
• Local Impact Reports (LIRs) from any Local Authorities;
• Statements of Common Ground (SoCG) requested by the ExA;
• Responses to the ExA’s First Written Questions;
• Comments on updated application documents;
• Responses to further information requested by the ExA;
• Post hearing submissions including written submissions of oral case;
• Notification of wish to speak at any subsequent Issue Specific Hearing (ISH);
• Notification of wish to speak at a Compulsory Acquisition (CA) Hearing;
• Notification of wish to make oral representations at the later Issue Specific Hearing on the dDCO (if required);
• Notification of wish to speak at an Open Floor Hearing (OFH);
• Provision of suggested locations and justifications for site inspections for consideration by the ExA;
• Notification of wish to attend an Accompanied Site Inspection (ASI).
View the documents received relating to this deadline
 Date Passed
30 November 2018
Deadline for receipt by the ExA of:
• Comments on WRs and responses to comments on RRs;
• Comments on LIRs;
• Comments on responses to the ExA’s Written Questions;
• Revised dDCO from Applicant;
• Comments on any additional information/ submissions received by D1;
• Responses to further information requested by the ExA for this deadline.
View the documents received relating to this deadline
 Date Passed
12 December 2018
CA Hearing
Compulsory Acquisition Hearing.
 Date Passed
12 December 2018
Open Floor Hearing
Open Floor Hearing.
 Date Passed
13 December 2018
Issue Specific Hearing
Issue Specific Hearing on the draft Development Consent Order.
 Date Passed
13 December 2018
Issue Specific Hearings
Issue Specific Hearing on Environmental Matters.
 Date Passed
14 December 2018
Accompanied Site Inspection
Accompanied Site Inspection.
 Date Passed
21 December 2018
Deadline 3
Deadline for receipt by the ExA of:
• Post hearing submissions including written submissions of oral case;
• Responses to further information requested by the ExA;
• Comments on any additional information/ submissions received by D2.
 Date Passed
11 January 2019
Publication by the ExA of
The ExA’s Further Written Questions (if required).
 Date Passed
01 February 2019
Deadline for receipt by the ExA of:
• Responses to further information requested by the ExA for this deadline;
• Any revised/ updated SoCGs;
• The Applicant’s revised dDCO;
• Comments on any additional information/ submissions received by D3;
• Responses to the ExA’s Further Written Questions (if required);
• The Applicant’s preferred DCO in the SI template validation report;
• Comments on any additional information/ submissions received by D3.
View the documents received relating to this deadline
 Date Passed
15 February 2019
Deadline for receipt by the ExA of:
• Post hearing submissions including written submissions of oral case;
• Any revised/ updated SoCG;
• Responses to further information requested by the ExA for this deadline;
• Comments on the Applicant’s revised dDCO;
• Comments on any additional information/submissions received by D4.
View the documents received relating to this deadline
 Date Passed
04 March 2019
Publication by the ExA
• The ExA’s dDCO (if required);
• Report on the Implications for European Sites (RIES) (if required).
 Date Passed
18 March 2019
Deadline for receipt by the ExA of:
• Comments on the ExA’s dDCO (if required);
• Responses to further information requested by the ExA;
• Responses to further information requested by the ExA for this deadline;
• Comments on any additional information/ submissions received by D5;
• Final DCO to be submitted by the Applicant in the SI template with the SI template validation report.
View the documents received relating to this deadline
 Date Passed
22 March 2019
Rule 17
Reserved for issue of any R17 requests for further information
 Date Passed
04 April 2019
• Any responses to R17 requests;
• Any responses to the RIES (if required).
View the documents received relating to this deadline
 Date Passed
10 April 2019
The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.
 Date Passed
10 April 2019
Examination closed