This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.
Event Date | Description |
---|---|
![]() | Examination Begins |
![]() | Open Floor Hearing 1 Open Floor Hearing (OFH1) |
![]() | Issue by ExA of - • Examination Timetable• The ExA’s Written Questions |
![]() | DEADLINE 1 Deadline for receipt of: • Comments on updated application documents • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Post Hearing submissions including written submissions of oral case made at OFH1 • Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Draft itinerary for Accompanied Site Inspection (ASI) • Notification of wish to speak at any subsequent Open Floor Hearing (OFH) • Notification of wish to make oral representations at an Issue Specific Hearing (ISH) • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • Notification of wish to have future correspondence received electronically • Comments on any additional information/submissions received • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | DEADLINE 2 Deadline for receipt of: • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Local Impact Reports from any local authorities • Statements of Common Ground (SoCG) requested by the ExA (except those requested between the applicant and statutory undertakers) • Responses to the ExA’s Written Questions • Applicant’s first revised draft DCO • Responses to comments on RRs • Comments on draft itinerary for ASI and suggested locations for site inspections • Comments on any additional information/submissions received by D1 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | DEADLINE 3 Deadline for receipt of: • Comments on WRs • Comments on Local Impact Reports • Comments on SoCGs • Comments on responses to the ExA’s Written Questions • Comments on applicant’s first revised draft DCO • Notification of wish to attend an ASI • Comments on any additional information/submissions received by D2 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Accompanied Site Inspection Accompanied Site Inspection |
![]() | Accompanied Site Inspection (continued) Date reserved to continue Accompanied Site Inspection (ASI) (if required) |
![]() | Issue Specific Hearing 1 (ISH1) Date reserved to hold ISH1 |
![]() | Issue Specific Hearing 2 (ISH2) Date reserved to hold ISH2 |
![]() | Open Floor Hearing (OFH2) Date reserved to hold OFH2 (evening) |
![]() | Compulsory Acquisition Hearing 1 (CAH1) Date reserved to hold CAH1 (afternoon) |
![]() | Issue Specific Hearing 3 (ISH3) Date reserved to hold ISH3 (morning) |
![]() | Issue Specific Hearing 4 (ISH4) Date reserved to hold ISH4 on the dDCO |
![]() | DEADLINE 4 Deadline for receipt of: • Post Hearing submissions including written submissions of oral case • SoCG's between the Applicant and Statutory Undertakers • Any revised/updated SoCG (if any) • Comments on any additional information/submissions received by D3 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Publication by ExA of - • The ExA's further Written Questions (if required) |
![]() | DEADLINE 5 Deadline for receipt of: • Responses to the ExA's further Written Questions (if required) • Applicant's revised draft DCO • Comments on any revised/updated SoCGs • Comments on any additional information/submissions received by D4 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Publication by the ExA of - • Report on the Implications for European Sites (RIES)• ExA’s proposed schedule of changes to the dDCO (if required) / or the ExA's draft DCO (if required) |
![]() | Publication by the ExA of - • The ExA's Additional Written Questions |
![]() | DEADLINE 6 (D6) Deadline for receipt of: • Comments on responses to the ExA’s further Written Questions, issued on 22 March 2019 • Comments on applicant’s revised draft DCO • Comments on any additional information/submissions received by D5 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | DEADLINE 6a (D6a) Deadline for receipt of: • Responses to the ExA’s Additional Written Questions View the documents received relating to this deadline |
![]() | Further Issue Specific Hearing (ISH5) Date reserved to hold ISH5 |
![]() | Further Issue Specific Hearing (ISH6) Date reserved to hold ISH6 on dDCO |
![]() | Further Open Floor Hearing (OFH3) Date reserved to hold OFH3 |
![]() | Further Issue Specific Hearing (ISH7) (If required) Date reserved to continue ISH5 and ISH6 if required |
![]() | Hearings (in accordance with the CA Regs) Date reserved to hold:• Further Issue Specific Hearing • Further Compulsory Acquisition Hearing • Further Open Floor Hearing |
![]() | DEADLINE 7 (D7) Deadline for receipt of: • Post Hearing submissions including written submissions of oral case (if required) • Comments on the RIES • Written Representations on the proposed provision to amend the application and include additional land • Comments on responses to the ExA’s Additional Written Questions, issued on 25 April 2019 • Applicant’s revised draft DCO (if required) • Comments on any additional information/submissions received by D6 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Publication by the ExA of - • The ExA’s proposed schedule of changes to the draft DCO (if required) |
![]() | DEADLINE 8 (D8) Deadline for receipt of: • Response to comments on the RIES • Final DCO to be submitted by the applicant in the SI template with the SI template validation report • Final updated Book of Reference • Final SoCGs • Final Compulsory Acquisition Schedule • Final updated Guide to the Application • Comments on any additional information/submissions received by D7 • Responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting. |
![]() | Examination closed |