Enquiry received via email
Enquiry from Les Stevens by email on 23 November 2018:

Could you clarify a couple of points on the Inspectors request for interested parties to work with the Applicant to draw up SoCG please?

One area requires the Applicant to draw up a SoCG with the Parish Councils of Queen Camel, Sparkford and West Camel on a number of issues raised in our formal joint submission or separate individual submissions.

Could you please provide clarification on two areas please -
1) Mott-MacDonald have contacted all three PCs separately offering to draft a SoCG with each - is the Inspectors expectation that this should be a single joint document rather than three separate ones?

2) The Hazelgrove junction appears to be missing from the list of items the Joint PCs are expected to draw up a SoCG with the Applicant - is this an omission or is the Inspectors expectation that this junction would be covered under the SoCG with Heritage England?

Clarification on these points would be helpful.

Many thanks.
Advice given by email on 29 November 2018:

Dear Les Stevens

I can confirm that the Examining Authority are content to receive either a joint SoCG or three individual SoCG’s. There is considerable overlap between the three Parish Councils and therefore a joint SoCG may be the most efficient way forward, this could include any points specific to the individual Parish Councils. The ExA however is content to receive individual SoCG if that proves more efficient for the Parish Councils.

Please note that the matters indicated in Annex G of the Rule 6 letter, dated 14 November 2018, are not the only matters that can be included in the SoCG(s). Should the parties be in a position to agree matters in relation to the Hazelgrove Junction (including identifying areas where there is disagreement), or any other matters, this would be helpful to the examination and should be included in the SoCG.

Kind regards

29 November 2018
Queen Camel, Sparkford & West Camel Parish Council - Les Stevens
Enquiry received via phone
response has attachments
Telephone enquiry from Mr Walton on 17 October 2018 regarding Relevant Representations.
Advice given by email on 18 October 2018:

Dear Mr Walton,

Following our telephone conversation yesterday I am emailing to confirm that the relevant representations period for the above mentioned project closes tomorrow Friday 19 October 2018 at 23:59. For information please refer to the project page on the National Infrastructure Planning website, see link below:

[attachment 1]

I also attach a link below to the Planning Inspectorate Advice Note 8.2: How to register to participate in an Examination. This advice note provides practical advice about registering a Relevant Representation in order to become an Interested Party. It also explains that once the Examination has started, you can continue to rely on the Relevant Representation you submitted in order to register as an Interested Party or you can submit a further written representation by the deadline that will be set out in the Examination Timetable. This can expand on the matters included in your Relevant Representation.

[attachment 2]

I hope you find the above information useful. Please note the Project Mailbox email address is [email protected]

18 October 2018
Mr Walton
Enquiry received via meeting
response has attachments
Teleconference to discuss submission logistics.
See attached meeting note.

05 July 2018
Highways England - anon.
Enquiry received via meeting
response has attachments
Meeting to provide feedback on draft application documents provided by Highways England.
See attached meeting note.

31 May 2018
Highways England - anon.
Enquiry received via meeting
response has attachments
Project Update Meeting
Please see attached Meeting Note

17 April 2018
Highways England
Enquiry received via meeting
response has attachments
Scoping clarifications and project update meeting
Please see attached

12 January 2018
Highways England - anon.
Enquiry received via meeting
response has attachments
Inception Meeting
Please see attached

08 November 2017
Highways England - anon.