Preview
Enquiry received via email
response has attachments
Response to actions arising from the draft document feedback and project update meeting held on 30 May 2018.
1. You asked for an example(s) of a good Statement of Reasons. I would first caveat that we haven’t really seen a ‘belt and braces’ SoR which hasn’t required a degree of examination to a greater or lesser extent. That said, the SoR for North London Heat and Power may be helpful if you’re looking for a steer - it is particularly helpful in respect of the detail/justification provided in its plot-by-plot approach to establishing need: [attachment 1]
2. You asked for examples of Land Plans in which insets had been used to articulate concentrations of smaller plots. These are helpfully applied in, amongst others, the Land Plans for:
o Thames Tideway Tunnel: [attachment 2]
o Norwich Northern Distributor Road: [attachment 3]
3. You asked for examples of the observations we made in respect of the landmarks used in the descriptions of some plots in the BoR, and their apparent absence from the Land Plans. The following landmarks are used in the BoR but are not annotated on the corresponding Land Plan sheets:
o ‘Blackwater Roundabout’ on Land Plan sheet 1 (Plots 1/1f, 1/1h and 1/1j)
o ‘Greenacres Farm’ on Land Plan sheet 1 (Plot 1/7)
o ‘Silverdene Farm’ on Land Plan sheet 2 (Plot 2/2)
4. John asked for clarification in respect of question nos. 16 and 19 of the draft DCO and EM commentary:
o Question no. 16 re. A24: simply that the Article only provides for extinguishment, but the Schedule title (and content) refers also to provision of new highways and private means of access. Which is right?
o Question no. 19 re. A34: we now note that there is a definition of ‘public utility undertaker’ in A34(4) as meaning gas, water electricity and sewerage undertakers – although those terms should perhaps also be defined?

31 May 2018
Highways England - anon.
Enquiry received via meeting
response has attachments
Draft document feedback and project update meeting
Please see attached meeting note

30 May 2018
Highways England - anon.
Enquiry received via meeting
response has attachments
Consultation feedback meeting
See attached meeting note

29 March 2018
Highways England - anon.
Enquiry received via meeting
response has attachments
Update meeting for the Applicant to outline the consultation materials and approach
Please see the attached meeting note

23 January 2018
Highways England - Josh Hodder
Enquiry received via meeting
response has attachments
Inception Meeting to discuss the A30 Chiverton to Carland Cross scheme
Please see the attached meeting note

14 June 2017
Highways England - Josh Hodder