Thanet Extension Offshore Wind Farm

You can filter the results to show only the items that match your interest.

Documents Published By Stage

Pre Application (7)

Developer's Application (149)

Acceptance (10)

Pre Examination (14)

Examination (758)

Decision (32)

Decided (0)

Date

SourceDescription
Other
Size: 353 KB
Estuary Services Limited
Deadline 7 Submission - Draft Statement of Common Ground
Other
Size: 1 MB
Marine Management Organisation
Deadline 7 Submission - Comments on responses to the Examining Authority's Further Written Questions (ExQ3), Responses to the ExA’s Further requests for information under EPR Rule 17 and Comments on the Applicant’s Draft Development Consent Order (dDCO) Revision F
Other
Size: 259 KB
Maritime and Coastguard Agency
Deadline 7 Submission - Cover letter, Responses to the ExA’s Further requests for information under EPR Rule 17 and Response to comments on the ExA's dDCO Commentary
Other
Size: 223 KB
Natural England
Deadline 7 Submission - Cover letter and comments on documents submitted by the applicant at Deadline 6 and in the period leading up to Deadline 7
Other
Size: 440 KB
Natural England
Deadline 7 Submission - Response to comments on the Examining Authority's dDCO Commentary
Other
Size: 172 KB
Natural England
Deadline 7 Submission - Comments on Responses to the ExA’s Further requests for information under EPR Rule 17
Other
Size: 177 KB
Natural England
Deadline 7 Submission - Deadline 7 Submission - Comments on responses to the Examining Authority's Further Written Questions (ExQ3)
Other
Size: 235 KB
Natural England
Deadline 7 Submission - Response to the Applicant's comments on RIES
Other
Size: 613 KB
Port of London Authority
Deadline 7 Submission - Draft Statement of Common Ground
Other
Size: 227 KB
Port of London Authority and Estuary Services Limited
Deadline 7 Submission - Response to the Applicant's Deadline 6 submissions, Comments on responses to the Examining Authority's Further Written Questions (ExQ3), Response to Deadline 5 Submission by Interested Parties, Response to ISH8 Hearing Action Point 20 requested for Deadline 7, Response to comments on the Examining Authority's dDCO Commentary
Other
Size: 437 KB
Port of Tilbury London Limited and London Gateway Port Limited
Deadline 7 Submission - Response to the Applicant's Deadline 6 submissions, Comments on Responses to the ExA’s Further requests for information under EPR Rule 17, Comments on responses to the Examining Authority's DCO commentary and final overall submissions and closing remarks
Other
Size: 151 KB
Trinity House
Deadline 7 Submission - Deadline 7 Submission - Counsel's Opinion (Rebecca Clutten FTB) on the Applicant’s Draft Development Consent Order (dDCO) Revision F (arbitration and saving provision for THLS)
Other
Size: 149 KB
Trinity House
Deadline 7 Submission - Deadline 7 Submission - Cover letter and Comments on the Applicant’s Draft Development Consent Order (dDCO) Revision F
Other
Size: 8 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 18 to Deadline 7 Submission: Statement of Common Ground – Port of London Authority (Signed). Late Submission accepted at the discretion of the Examining Authority
Other
Size: 353 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 19 to Deadline 7 Submission: Statement of Common Ground – Estuary Services Limited
Other
Size: 9 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 19 to Deadline 7 Submission: Statement of Common Ground – Estuary Services Limited (Signed). Late Submission accepted at the discretion of the Examining Authority
Other
Size: 185 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 13 to Deadline 7 Submission: ExQ 1.3.7 Statutory Undertakers Land Rights table
Other
Size: 184 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 10 to Deadline 7 Submission: List of All Objections to the Grant of Compulsory Acquisition and Temporary Possession Powers (ExQ 1.3.6)
Other
Size: 202 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 15 to Deadline 7 Submission: Outline Shipping and Navigation Liaison Plan
Other
Size: 1 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 16 to Deadline 7 Submission: Applicant’s position on Shipping and Navigation Future Baseline
Other
Size: 835 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 17 to Deadline 7 Submission: Statement of Reasons - Revision B
Other
Size: 545 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex A to Appendix 8 to Deadline 7 Submission: Schedule of Mitigation (Tracked changes since Deadline 3)
Other
Size: 613 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 18 to Deadline 7 Submission: Statement of Common Ground – Port of London Authority
Other
Size: 202 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 11 to Deadline 7 Submission Landowner Agreements Update Table
Other
Size: 200 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 12 to Deadline 7 Submission: Commercial Agreements Update Table
Other
Size: 181 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 14 to Deadline 7 Submission: ExQ 1.3.8 Statutory Undertakers Apparatus table
Other
Size: 227 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 20 to Deadline 7 Submission: Statement of Common Ground - Thanet Fishermen’s Association
Other
Size: 1 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex A to Appendix 6 to Deadline 7 Submission: Log of Changes to the draft Development Consent Orde
Other
Size: 2 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 5 to Deadline 7 Submission: Revised Draft Development Consent Order - Revision H
Other
Size: 422 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex E to Appendix 6 to Deadline 7 Submission: Applicant’s response to ExA’s further requests for information under EPR Rule 17 – 4.1.5
Other
Size: 410 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex A to Appendix 2 to Deadline 7 Submission: Collation of responses to Interested Parties on submissions relating to the navigational simulation
Other
Size: 510 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex B to Appendix 2 to Deadline 7 Submission: Email Correspondence
Other
Size: 413 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 4 to Deadline 7 Submission: Applicant's Response to Deadline 6 Interested Parties Submissions – Other Matters
Other
Size: 736 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 3 to Deadline 7 Submission: Responses to IP Comments on the ExA's DCO Commentary
Other
Size: 1 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex A to Appendix 5 to Deadline 7 Submission: SI Template Validation Report
Other
Size: 794 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex D to Appendix 6 of Deadline 7 Submission – Offshore Project Description Assessed in the Environmental Statement
Other
Size: 2 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 2 to Deadline 7 Submission: Applicant's Response to Deadline 6 Interested Parties Submissions - Shipping and Navigation
Other
Size: 626 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex B to Appendix 6 to Deadline 7 Submission: Explanatory Memorandum – Tracked Changes
Other
Size: 2 MB
Vattenfall Wind Power Limited
Deadline 7 Submission - Annex C to Appendix 6 to Deadline 7 Submission: Revised Draft Development Consent Order Tracked Changes
Other
Size: 964 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 1 to Deadline 7 Submission: Guide to the Application
Other
Size: 651 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 8 to Deadline 7 Submission: Schedule of Mitigation
Other
Size: 797 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 6 to Deadline 7 Submission: Explanatory Memorandum
Other
Size: 239 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 21 to Deadline 7 Submission: Requests for Statements of Common Ground and Statement of Commonality – Shipping and Navigation
Other
Size: 377 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 7 to Deadline 7 Submission: Requests for Statements of Common Ground and Statement of Commonality
Other
Size: 282 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 27 to Deadline 7 Submission: Shipping and Navigation: Schedule of Mitigation
Other
Size: 554 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 28 to Deadline 7 Submission: Applicant’s commentary on responses to the ExA’s further requests for information under EPR Rule 17
Other
Size: 59 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Cover Letter
Other
Size: 316 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 24 to Deadline 7 Submission: Statement of Common Ground – Chamber of Shipping-
Other
Size: 191 KB
Vattenfall Wind Power Limited
Deadline 7 Submission - Appendix 9 to Deadline 7 Submission: Planning Act 2008 s.135 Crown Land and Consent