Morgan Offshore Wind Project Generation Assets
Enquiry
The Inspectorate attended an online Steering Group for the Morgan Generation Assets and Mona Offshore Wind Projects. The meeting provided a project update, details of an updated methodology for the Habitats Regulations Assessment (HRA), and an overview of key responses to the recent statutory consultation. The Applicant also outlined its proposed approach to the cumulative effects assessment (CEA) for the Morgan Generation project and requested any comments on the approach.
Advice given
The Inspectorate advised that the CEA is undertaken on the basis of applicable worst case scenarios for the Proposed Development and other development, taking into account the information available at the time of assessment. The Inspectorate confirmed it had no further comments on the CEA at this stage.