York Potash Harbour Facilities Order

What happens next

A decision on the application for a Development Consent Order for York Potash Harbour Facilities Order was taken on 20 July 2016.

Timeline (10 items)

The Examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

26 May 2023
Decision made by the Secretary of State
20 July 2016
Recommendations given by the Planning Inspectorate
20 April 2016
  • Preliminary Meeting takes place
  • Examination begins
21 July 2015
Relevant representations published on the website
12 June 2015
Registration of interested parties closes
08 June 2015
Registration of interested parties begins
29 April 2015
Decision on whether or not to accept the application for examination
21 April 2015
Application received by the Planning Inspectorate
27 March 2015