This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.
Event Date | Description |
---|---|
![]() | Examination Begins |
![]() | Issue Specific Hearing 1 (ISH1) ISH1 on the draft Development Consent Order(dDCO) |
![]() | Open Floor Hearing (OFH1) Open Floor Hearing (OFH1) |
![]() | Issue by the ExA of - • Examination Timetable• The ExA's Written Questions (ExQ1) |
![]() | Deadline 1 For receipt by ExA of: • comments on any updates to application documents submitted by the Applicant before or at the PM • comments on Relevant Representations (RRs) • summaries of all RRs exceeding 1500 words • Written Representations (WRs) by all Interested Parties (IPs) • summaries of all WRs exceeding 1500 words • Statements of Common Ground (SoCG) requested by ExA – see Annex G of the Rule 6 letter • notification by Statutory Parties of their wish to be considered as an IP by the ExA • notification of wish to speak at any subsequent Issue Specific Hearings (ISH) • notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • notification of wish to speak at any subsequent Open Floor Hearing (OFH) • notification of wish to attend an Accompanied Site Inspection (ASI) • provision of suggested locations and justifications for site inspections for consideration by the ExA • Draft Itinerary to be provided by the Applicant for an ASI • post-hearing submissions including written submissions of oral cases and • notification of wish to have future correspondence received electronically View the documents received relating to this deadline |
![]() | Deadline 2 For receipt by ExA of: • comments on WRs • any revised/updated SoCGs • Local Impact Reports (LIR) from any Local Authorities • responses to ExA’s Written Questions (ExQ1) • comments on any updates to Application Documents submitted by the Applicant • the Applicant’s revised dDCO • post-hearing submissions including written submissions of oral cases • response to any further information requested by the ExA for this deadline • comments on any additional information/submissions received by Deadline 1 • Applicant to submit report on consultation undertaken about proposed change to the Application – see Annex B • Applicant to submit clarification document on how the proposed changes would be secured through the DCO View the documents received relating to this deadline |
![]() | Accompanied Site Inspection (ASI) Accompanied Site Inspection (ASI) |
![]() | Open floor Hearing (OFH2) Open floor Hearing (OFH2) |
![]() | Issue Specific Hearing 2 (ISH2) Issue Specific Hearing 2 (ISH2):ISH2 on the interrelationship of major proposals in the area, environmental & landscape/visual issues and transport matters |
![]() | Compulsory Acquisition Hearing (CAH1) Compulsory Acquisition Hearing (CAH1) |
![]() | Issue Specific Hearing 3 (ISH3) Issue Specific Hearing 3 (ISH3):ISH3 on the draft Development Consent Order (dDCO) |
![]() | Deadline 3 For receipt by ExA of: • any revised/updated SoCGs • comments on LIRs • comments on responses to ExA’s Written Questions (ExQ1) • post-hearing submissions including written submissions of oral cases • the Applicant’s revised dDCO • responses to any further information requested by the ExA for this deadline • comments on the Applicant’s proposed changes to the Application • comments on any additional information/submissions received by Deadline 2 View the documents received relating to this deadline |
![]() | Deadline 4 For receipt by ExA of: • comments on the Applicant’s revised dDCO • comments on any revised/updated SoCGs (if any) • comments on any additional information/submissions received by Deadline 3 • responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Publication by ExA of - • Further Written Questions (ExQ2)• the ExA’s preferred dDCO or dDCO commentary |
![]() | Deadline 5 For receipt by ExA of: • responses to ExQ2 • comments on the ExA’s preferred dDCO or dDCO commentary • final signed SoCGs • comments on any additional information/submissions received by Deadline 4 • responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Deadline 6 For receipt by ExA of: • comments on responses to ExQ2 • the Applicant’s Final Preferred DCO in the SI template validation report • comments on any final signed SoCGs • comments on any additional information/submissions received by Deadline 5 • responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Deadline 7 For receipt by ExA of: • comments on the Applicant’s Final Preferred DCO • responses to any further information requested by the ExA for this deadline • comments on any additional information/submissions received by Deadline 6 • responses to any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Deadline 8 For receipt by ExA of: • Applicant’s response to ExA’s request for further information • comments on any additional information/submissions received by Deadline 7 |
![]() | Deadline 9 For receipt by ExA of: • comments on Applicant’s response to ExA’s request for further information • comments on any additional information/submissions received by Deadline 8 View the documents received relating to this deadline |
![]() | The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting. The ExA may close the examination before the end of the six month period if he is satisfied that all relevant matters have been addressed and discussed. |
![]() | Examination closed |