Riverside Energy Park

This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.

Event DateDescription
 Date Passed
10 April 2019
Examination Begins
 Date Passed
17 April 2019
Issue by the Examining Authority (ExA)
Issue by the ExA of:
-Examination Timetable
-The ExA's Written Questions
 Date Passed
30 April 2019
Deadline 1 for the receipt of:
- Notification of wish to speak at a Compulsory Acquisition Hearing
- Notification of wish to speak at an Issue Specific Hearing
- Notification of wish to speak at an Open Floor Hearing
- Notification of wish to attend an Accompanied Site Inspection (ASI), suggested locations and justifications
- Notification by statutory parties of wish to be considered as an Interested Party
- Notification of wish to have future correspondence electronically
- Provision by the Applicant of a draft itinerary for the ASI
- Responses to any further information requested by the ExA for this Deadline
View the documents received relating to this deadline
 Date Passed
20 May 2019
Deadline 2 for receipt of:
- Comments on Relevant Representations (RRs)
- Written Representations (WRs)
- Summaries of all WRs exceeding 1500 words
- Local Impact Reports (LIR) from any local authorities
- Statements of Common Ground(s) (SoCGs) requested by the ExA
- Responses to the ExA’s Written Questions
- Provision by the Applicant of final itinerary for ASI
- Comments on any additional information/submissions received by previous deadline
- Responses to any further information requested by the ExA for this Deadline
View the documents received relating to this deadline
 Date Passed
04 June 2019
Accompanied Site Inspection
Date reserved for accompanied site inspection
 Date Passed
04 June 2019
Open Floor Hearing
Open floor hearing
 Date Passed
05 June 2019
Issue Specific Hearing (ISH1)
Issue specific hearing (ISH1) on environmental matters
 Date Passed
06 June 2019
Compulsory Acquisition Hearing (CAH1)
Compulsory Acquisition Hearing (CAH1)
 Date Passed
06 June 2019
Issue Specific Hearing (ISH2)
Issue specific hearing (ISH2) on the draft Development Consent Order
 Date Passed
07 June 2019
Compulsory Acquisition Hearing (CAH1) continued
Continuation of CAH1 of 6 June 2019
 Date Passed
18 June 2019
Deadline 3 for receipt by the ExA of:
- Comments on WRs and responses to comments on RRs
- Comments on LIRs
- Comments on responses to the ExA’s First Written Questions
- Any revised SoCGs
- Revised draft DCO from Applicant
- Post hearing submissions including written submissions of oral case
- Responses to any further information requested by the ExA
- Comments on any additional information/submissions received by previous deadline
View the documents received relating to this deadline
 Date Passed
19 July 2019
Deadline 4 for receipt of:
- Responses to the ExA’s Further Written Questions (if required)
- Comments on Applicant’s revised draft DCO (if required)
- Comments on Post hearing submissions including written submissions of oral case
- Any revised SoCG
- Responses to any further information requested by the ExA
- Comments on any additional information/submissions received by previous deadline
View the documents received relating to this deadline
 Date Passed
13 August 2019
Deadline 5 for receipt of:
- Applicant’s revised draft DCO
- Responses to further information requested by the ExA
- Any revised SoCG
- Post hearing submissions including written submissions of oral case
- Responses to any further information requested by the ExA
- Comments on any additional information/submissions received by previous deadline
View the documents received relating to this deadline
 Date Passed
16 August 2019
Deadline 6 for receipt of:
- Responses to the ExA’s further written questions
and request for comments on changes to the application issued on 1 August 2019
View the documents received relating to this deadline
 Date Passed
03 September 2019
Deadline 7 for receipt of:
- Comments on the draft DCO (if required)
- Any revised SoCG
- Responses to any further information requested by the ExA
- Comments on any additional information/submissions received by previous deadline
View the documents received relating to this deadline
 Date Passed
13 September 2019
Deadline 7a for receipt of:
• Responses to any further information requested by the ExA
• Comments on any additional information/submissions received by previous deadlines
View the documents received relating to this deadline
 Date Passed
18 September 2019
Compulsory Aquisition Hearing (CAH2)
Compulsory Acquisition Hearing (CAH2)
 Date Passed
19 September 2019
Issue Specific Hearing (ISH3)
Issue Specific Hearing (ISH3) into the draft Development Consent Order (DCO)
 Date Passed
23 September 2019
Deadline 8 for receipt of:
- Responses to comments on the draft DCO (if required)
- Responses to any further information requested by the ExA
- Final SoCGs
- Comments on any additional information/submissions received by previous deadline
- Final draft DCO to be submitted by the Applicant in the statutory instrument (SI) template with the SI template validation report
View the documents received relating to this deadline
 Date Passed
30 September 2019
Deadline 8a for receipt of:
- Response to any further information requested by the ExA
- Comments on any additional information/submissions received by the previous deadline
- Final SoCGs
- Final draft DCO to be submitted by the Applicant in the statutory instrument (SI) template with the SI template validation report
- Final Explanatory Memorandum and final schedule of changes to the DCO to be submitted by the Applicant
View the documents received relating to this deadline
 Date Passed
04 October 2019
Deadline 8b for receipt of:
- Comments on the Applicants Final draft DCO, Explanatory Memorandum and schedule of changes
- Response to any further information requested by the ExA
- Comments on any additional information/submissions received by the previous
deadline
View the documents received relating to this deadline
 Date Passed
09 October 2019
Examination closed