This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.
Event Date | Description |
---|---|
![]() | Examination Begins |
![]() | Rule 8 letter Issue of:• Examination timetable • ExA’s first written questions |
![]() | Deadline 1 Deadline for receipt by the ExA of • Summaries of all relevant representations (RR) submitted by 23 December 2015 exceeding 1500 words • Comments on RRs • Notification by statutory parties of wish to be considered as an interested party • Notification by persons within certain categories of interests on the land of wish to become an interested party • Notification by interested parties of wish to make oral representations at the issue specific hearing on the draft Development Consent Order (DCO) to be held on 18 March 2016 • Notification by affected persons of wish to speak at a compulsory acquisition hearing • Notification by interested parties of wish to speak at an open floor hearing • Submissions from interested parties recommending locations or items for the itinerary for the accompanied site inspection on 17 March 2016 • Any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Site Visit (Accompanied) A site inspection in the company of interested parties, taking in the project site and surrounding areas. |
![]() | Issue Specific Hearing Issue specific hearing on the draft Development Consent Order. |
![]() | Deadline 2 • Written representations (WRs) by all interested parties All parties should submit their full written case and supporting evidence at this stage, as any representations to be heard at a hearing should be based on RR or WR. • Summaries of all WRs exceeding 1500 words View the documents received relating to this deadline |
![]() | Deadline 3 Deadline for receipt by ExA of: • Written summaries of oral submissions put at the issue specific hearing dealing with matters relating to the draft DCO held on 18 March 2016 • Responses to the ExA’s first written questions • Local Impact Reports (LIR) from local authorities • Statements of Common Ground (SoCG) requested by the ExA • Updated draft DCO from the applicant • Any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Deadline 4 Deadline for receipt by the ExA of: • Comments on WRs and any responses to comments on RRs • Comments on LIR • Comments on responses to the ExA’s first written questions • Any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Publication of ExA Second Questions Publication by the ExA of:• Second written questions |
![]() | Deadline 5 Deadline for receipt of: • Responses to the ExA’s second written questions • Any further information requested from the ExA for this deadline View the documents received relating to this deadline |
![]() | Deadline 6 Deadline for receipt of: • Comments on responses to the ExA’s second written questions • Any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Issue Specific Hearing on the Draft Development Consent Order Issue Specific Hearing on the Draft Development Consent Order, 10.00am (Doors open 9.30am) |
![]() | Open Floor Hearing (afternoon) Open Floor Hearing, 2.00pm (Doors open 1.30pm) |
![]() | Open Floor Hearing (evening) Open Floor Hearing, 6.00pm (Doors open 5.30pm) |
![]() | Compulsory Acquisition Hearing Compulsory Acquisition Hearing, 10.00am (Doors open 9.30am) |
![]() | Deadline 7 Deadline for receipt of: • Written summaries of oral submissions put at any hearings held between 27 June and 8 July • Any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Publication of RIES Publication by the ExA of:• Report on Implications for European Sites (RIES) if required |
![]() | Accompanied Site Visit Wednesday 17 August 2016.Accompanied Site Visit |
![]() | Deadline 8 Deadline for receipt of: • Written summaries of oral submissions put at any hearings held on 17 and 18 August • Applicant’s final draft DCO and Explanatory Memorandum • Comments on the ExA’s RIES (if required) • Any further information requested by the ExA for this deadline View the documents received relating to this deadline |
![]() | Examination closed |