North London Heat and Power Project

The list below includes a record of advice we have provided for this project. For a list of all advice issued by the Planning Inspectorate, including non-project related advice, please go to the Register of advice page.

There is a statutory duty, under section 51 of the Planning Act 2008, to record the advice that is given in relation to an application or a potential application, including the name of the person who requested the advice, and to make this publicly available.

Preview
response has attachments
Meeting regarding a potential non-material change request
Please see the attached meeting note

09 November 2017
North London Waste Authority - Ursula Taylor
Enquiry received via meeting
response has attachments
Request for review of draft application documents (Statement of Reasons and Funding Statement).
See attached.

12 October 2015
Arup - Katie Kerr
Enquiry received via email
response has attachments
See advice regarding combined heat and power requirements attached
See advice attached

05 October 2015
Arup - Katie Kerr
Enquiry received via phone
A request for clarity about points raised in the Planning Inspectorate advice on the draft HRA No Significant Effects Report.
The HRA report should be a standalone document and should provide a clear evidence trail to support the conclusions. It is not possible to comment on the adequacy of the information in the ES (to which the draft matrices in the Report refer) as the Inspectorate does not have sight of this. The referencing system in the draft matrices appears to be adequate but this did not preclude the ExA from asking questions in this regard.

02 October 2015
Nichola White on behalf of Arup
Enquiry received via meeting
response has attachments
See attached meeting note
See attached meeting note

01 October 2015
North London Waste Authority NLWA
Enquiry received via phone
response has attachments
Further advice regarding s.43 consultees
Please see attached advice

22 September 2015
Katie Kerr
Enquiry received via email
response has attachments
Request for review of application documents (No Significant Effects Report and draft Consultation Report) for the North London Heat and Power Project
See attached

22 September 2015
Arup - Katie Kerr
Enquiry received via meeting
response has attachments
See attached meeting note
See attached meeting note

04 September 2015
North London Waste Authority NLWA
Enquiry received via phone
response has attachments
Update regarding the concerns of the Environment Agency regarding the applicant?s proposed noise assessment methodology.
Please see attached.

25 August 2015
Environment Agency
Enquiry received via meeting
response has attachments
Request for advice relating to persons listed in both Parts 1 and 3 of the Book of Reference and whether to present the type of compulsory acquisition powers being sought in Part 1 of the Book of Reference.
See attached advice.

14 August 2015
Katie Kerr
Enquiry received via meeting
response has attachments
See attached meeting note
See attached meeting note

06 August 2015
North London Waste Authority NLWA
Enquiry received via email
response has attachments
Request for review of application documents (Development Consent Order, Explanatory Memorandum, Statement of Reasons, Book of Reference, and Land Works Plans) for the North London Heat and Power Project
See attached.

28 July 2015
Katie Kerr
Enquiry received via meeting
response has attachments
Request for review of application documents (HRA Screening) for the Notrth London Heat and Power Project
See attached.

09 July 2015
Katie Kerr
Enquiry received via email
response has attachments
Request for review of application documents (Consultation Report and Consents Schedule) for the North London Heat and Power Project
See attached.

09 July 2015
Katie Kerr
Enquiry received via phone
response has attachments
Anna von Borzyszkowska at the Environment Agency had recently met with the applicant and was concerned of their proposal to not follow the latest revision to the standard for assessing noise impacts. Apparently the applicant was relying on recent case law to support this but Anna wasn?t aware of what this was ? and so asked if PINS knew anything.
PINS stated that the applicant was probably best placed to advise on this and to seek clarity from them but provided the attached correspondence based on information provided by the Knowledge and Information team.

29 June 2015
Environment Agency
Enquiry received via email
response has attachments
Request for review of draft application documents for the North London Heat and Power Project, namely:

- Need Assessment
- Alternative Assessment Report.
Please see attached advice.

19 June 2015
North London Waste Authority - Katie Kerr
Enquiry received via meeting
response has attachments
Outreach event at EcoPark, Edmonton.
Please see attached meeting note and presentations given.

10 June 2015
Ursula Taylor
Enquiry received via meeting
response has attachments
Project update meeting
Please see the attached meeting note

27 May 2015
Ursula Taylor
Enquiry received via email
response has attachments
Applicant request for comments on the proposed methodology for assessing the potential environmental impacts of the proposed development.
Please see attached correspondence.

24 April 2015
North London Waste Authority
Enquiry received via meeting
response has attachments
Project update meeting
Please see the attached meeting note.

16 April 2015
Ursula Tayor
Enquiry received via meeting
response has attachments
Project update meeting
Please see attached meeting note.

26 March 2015
Ursula Taylor
Enquiry received via post
response has attachments
Applicant request for comments on the proposed approach to assessing the potential cumulative impacts of the proposed development.
Please see attached correspondence.

24 February 2015
North London Waste Authority
Enquiry received via meeting
response has attachments
Project update meeting
Please see attached meeting note

19 February 2015
Ursula Taylor
Enquiry received via meeting
response has attachments
Project update meeting
See attached meeting note

11 December 2014
Ursula Taylor
Enquiry received via meeting
response has attachments
Project update meeting
Please see attached meeting note.

12 November 2014
Ursula Taylor
Enquiry received via meeting
response has attachments
Introductory project meeting between the developer for the North London Heat and Power Project and the Planning Inspectorate.
Please see attached meeting note.

29 August 2014
Ursula Taylor