Documents Published By Stage

Pre Application (26)

Developer's Application (636)

Acceptance (9)

Pre Examination (498)

Examination (2996)

Decision (210)

Decided (1)

Transboundary Documents
Date

SourceDescription
Other
Alde and Ore Association (PDF, 130 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Aldeburgh Society (PDF, 152 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Alex Johnston (PDF, 336 KB)
Deadline 8 Submission
Other
Alison Shirreff (PDF, 170 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Alistair Johnson (PDF, 91 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Amanda Erlenbach (PDF, 100 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Amanda Taylor (PDF, 131 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Andy Mason (PDF, 35 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Anne Cardwell Ilanga (PDF, 91 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Annette Abbott (PDF, 153 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Anthony Webb (PDF, 864 KB)
Deadline 8 Submission
Other
Area of Outstanding Natural Beauty (AONB) (PDF, 335 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Betsy Lemmon (PDF, 143 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Bill Parker (PDF, 257 KB)
Deadline 8 Submission - Other: Comments on proposed desalination plant
Other
Bill Parker (PDF, 114 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 11 (ISH11) on Flooding, Water and Coastal Processes
Other
Bill Parker (PDF, 155 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Chris Wilson (PDF, 421 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Clare Rizzo (PDF, 90 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Cllr Josie Bassinette on behalf of Walberswick Parish Council (PDF, 135 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Create Consulting Engineers Ltd on behalf of LJ and EL Dowley (PDF, 289 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
Create Consulting Engineers Ltd on behalf of LJ and EL Dowley (PDF, 1 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
Create Consulting Engineers Ltd on behalf of the Grant Family (PDF, 1 MB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline - Fordley Hall
Other
Create Consulting Engineers Ltd on behalf of the Grant Family (PDF, 2 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
David and Belinda Grant (PDF, 3 MB)
Deadline 8 Submission
Other
David Humphrey (PDF, 96 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Diane Humphrey (PDF, 75 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Dr Frank Burdett (PDF, 175 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
East Anglia ONE North Limited (PDF, 316 KB)
Deadline 8 Submission
Other
East Anglia TWO Limited (PDF, 316 KB)
Deadline 8 Submission
Other
East Suffolk Council (PDF, 222 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
East Suffolk Council (PDF, 95 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3) - R.3 Radiological considerations
Other
East Suffolk Council (PDF, 2 MB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
East Suffolk Council (PDF, 184 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3) - G.3 General and cross-topic questions
Other
East Suffolk Council (PDF, 91 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)- DCO.3 Draft Development Consent Order (DCO)
Other
East Suffolk Council (PDF, 328 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 11 Flooding, Water and Coastal Processes 14 September 2021
Other
East Suffolk Council (PDF, 261 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 12 Community, Amenity and Recreation, Human Health, Living Conditions
Other
East Suffolk Council (PDF, 268 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 14 DCO, Code of Construction Practice and similar regulatory documents, Deed of Obligation, reasonable endeavours
Other
East Suffolk Council (PDF, 180 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
East Suffolk Council (PDF, 177 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3) - CC.3 Climate change and resilience
Other
East Suffolk Council (PDF, 207 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
East Suffolk Council (PDF, 156 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3) - Bio.3 Biodiversity and ecology, terrestrial and marine
Other
East Suffolk Council (PDF, 225 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 13 Landscape, Visual Impact, Design and Terrestrial Heritage
Other
East Suffolk Internal Drainage Board (PDF, 204 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
East Suffolk Internal Drainage Board (PDF, 302 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Elaine Heeler (PDF, 142 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Elizabeth Green (PDF, 200 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
English Heritage Trust (EHT) (PDF, 176 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
English Heritage Trust (EHT) (PDF, 9 MB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Sustainable Conservation and Management Strategy for Leiston Abbey
Other
Environment Agency (PDF, 230 KB)
Deadline 8 Submission - Comments on Coastal Geomorphology Reports
Other
Environment Agency (PDF, 306 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Environment Agency (PDF, 308 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7 - Comments on 3.1 Draft Development Consent Order - Revision 8.0 and 8.17 Draft Deed of Obligation - Revision 7.0
Other
Environment Agency (PDF, 266 KB)
Deadline 8 Submission - Responses to Change 19 Request
Other
Environment Agency (PDF, 167 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Environment Agency (PDF, 341 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7 - Comments on Deadline 7 Submission - 9.89 Draft Fish Monitoring Plan - Revision 1.0
Other
Environment Agency (PDF, 268 KB)
Deadline 8 Submission - Site Water Supply Strategy – Revision 2.0
Other
Erica Rae (PDF, 87 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Frances Crowe (PDF, 25 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
Frances Crowe (PDF, 137 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Georgina Baker (PDF, 94 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Guy Parry (PDF, 46 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Helen Riches (PDF, 220 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Historic England (PDF, 363 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
Ian Galloway (PDF, 92 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Ian Galloway (PDF, 143 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISH 14 Domestic and Non Domestic Potable Supply
Other
Ian Galloway (PDF, 225 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Ian Rose (PDF, 162 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Ipswich & East Clinical Commissioning Group (PDF, 200 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Irene Bard (PDF, 166 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Jackum Brown (PDF, 2 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Jennifer Wilson (PDF, 108 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Jeremy Solnick (PDF, 154 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Joan Girling (PDF, 2 MB)
Deadline 8 Submission
Other
John Parsons (PDF, 46 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
John Sutherell (PDF, 171 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISH 11
Other
John Sutherell (PDF, 405 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
John Sutherell (PDF, 149 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISSUE SPECIFIC HEARING (ISH) 12 ON WEDNESDAY 15 SEPTEMBER 2021
Other
John Sutherell (PDF, 544 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
John Sutherell (PDF, 83 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISSUE SPECIFIC HEARING (ISH) 13 ON THURSDAY 16 SEPTEMBER 2021
Other
John Sutherell (PDF, 83 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISSUE SPECIFIC HEARING (ISH) 13 ON FRIDAY 17 SEPTEMBER 2021
Other
Jon Alltree (PDF, 163 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Julia Brown (PDF, 96 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Justin and Emma Dowley (PDF, 89 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Kelsale-cum-Carlton Parish Council (PDF, 725 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Written Summary of Oral Submission (and update) to Issue Specific Hearing 12 on Community, Amenity and Recreational, Human
Other
Kelsale-cum-Carlton Parish Council (PDF, 613 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Kelsale-cum-Carlton Parish Council (PDF, 663 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Written Summary of Oral Submission (and update) to Issue Specific Hearing 11 on Flooding, Water and Coastal Processes
Other
Kelsale-cum-Carlton Parish Council (PDF, 1 MB)
Deadline 8 Submission - Responses to Change Request 19
Other
Laurence Moss (PDF, 207 KB)
Deadline 8 Submission
Other
Leiston Community Land Trust (PDF, 123 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Leiston-cum-Sizewell Town Council (PDF, 78 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 14 – The Development Consent Order, Deed of Obligation and Allied Documents
Other
Leiston-cum-Sizewell Town Council (PDF, 156 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 11 – Flooding, Water and Coastal Processes
Other
Leiston-cum-Sizewell Town Council (PDF, 137 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 12 – Community Matters
Other
Louise and Derek Chadwick (PDF, 195 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Marie Zabell (PDF, 230 KB)
Deadline 8 Submission
Other
Marine Management Organisation (MMO) (PDF, 195 KB)
Deadline 8 Submission - Post Hearing submissions including comments on Issue Specific Hearing 11 (ISH 11) and ISH14, Responses to the ExA's Third Written Questions (ExQ3), Comments on any additional information/ submissions received by D7, Responses to Change Request 19
Other
Mark Goyder (PDF, 217 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Marlesford Parish Council (PDF, 1 MB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Marlesford Parish Council (PDF, 573 KB)
Deadline 8 Submission - Other: Local parishes letter to East Suffolk Council re Southern Park and Ride
Other
Martin Howe (PDF, 178 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Mary George (PDF, 216 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Middleton cum Fordley Parish Council (PDF, 159 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 12: Community, Amenity and Recreational, Human
Other
Mike Taylor (PDF, 206 KB)
Deadline 8 Submission
Other
Mollett’s Partnership (trading as Mollett’s Farm) (PDF, 1 MB)
Deadline 8 Submission - Other: Deadline 8 Submission - Appendix B (Letter from Acoustical Control)
Other
Mollett’s Partnership (trading as Mollett’s Farm) (PDF, 1 MB)
Deadline 8 Submission
Other
Mr and Mrs Lacey (PDF, 806 KB)
Deadline 8 Submission
Other
Mrs Marina Baskett (PDF, 57 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Nadia Kuatois (PDF, 187 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
National Trust (PDF, 372 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Natural England (PDF, 273 KB)
Deadline 8 Submission - Natural England’s Response to The Examining Authority’s Request for Written Responses from Issue Specific Hearing 10
Other
Natural England (PDF, 115 KB)
Deadline 8 Submission - Natural England’s Comments on Revision 5 - 8 of DCO/DML & Deed of Obligation
Other
Natural England (PDF, 82 KB)
Deadline 8 Submission - Natural England’s Comments on the Permanent and Temporary Beach Landing Facility and SSSI Crossing Plans
Other
Natural England (PDF, 140 KB)
Deadline 8 Submission - Natural England’s Comments on Revision 1.0 Draft Fish Monitoring Plan
Other
Natural England (PDF, 124 KB)
Deadline 8 Submission - Cover Letter
Other
Natural England (PDF, 128 KB)
Deadline 8 Submission - Natural England’s Comments on the Water Monitoring Plan
Other
Natural England (PDF, 172 KB)
Deadline 8 Submission - Natural England’s Comments on the Site Water Supply Strategy
Other
Natural England (PDF, 133 KB)
Deadline 8 Submission - Natural England’s Comments on Fen Meadow Plan
Other
Natural England (PDF, 125 KB)
Deadline 8 Submission - Natural England’s Comments on Monitoring and Mitigation Plan for Sandlings (Central) and Alde, Ore and Butley Estuaries European Sites
Other
Natural England (PDF, 149 KB)
Deadline 8 Submission - Natural England’s response to Examining Authority’s follow-up questions to Natural England’s response to [EV-188], section 5, Marsh Harrier
Other
Natural England (PDF, 178 KB)
Deadline 8 Submission - Natural England’s briefing note on the detailed agenda for Issue Specific Hearing 15 on the Proposed Temporary Desalination Plant
Other
Natural England (PDF, 180 KB)
Deadline 8 Submission - Natural England’s Comments on White Fronted Geese Survey Report
Other
Natural England (PDF, 193 KB)
Deadline 8 Submission - Natural England’s Comments on Revision 2.0 Outline Vessel Management Plan
Other
Natural England (PDF, 169 KB)
Deadline 8 Submission - Natural England’s Response to The Examining Authority’s Third Written Questions
Other
Natural England (PDF, 125 KB)
Deadline 8 Submission - Natural England’s Comments on Draft Sabellaria Reef Management and Monitoring Plan
Other
Addleshaw Goddard LLP on behalf of Network Rail Infrastructure Limited (PDF, 59 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Nick Scarr (PDF, 342 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
Nick Scarr (PDF, 748 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
Nick Scarr (PDF, 10 MB)
Late Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Nicola Pilkington (PDF, 70 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Nigel Smith (PDF, 191 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
NNB Generation Company (SZC) Limited (PDF, 9 MB)
Deadline 8 Submission - 3.1 Ninth Draft DCO Addendum
Other
NNB Generation Company (SZC) Limited (PDF, 3 MB)
Deadline 8 Submission - 5.1 Consultation Report Fifth Addendum - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 24 MB)
Deadline 8 Submission - 2.10(B) Sizewell Link Road Plans for Approval 1 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 40 MB)
Deadline 8 Submission - 2.10(B) Sizewell Link Road Plans Not for Approval 1 of 2
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.10(E) Statement of Commonality of Statements of Common Ground
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 3 Description of Construction Appendix 3D of the Environmental Statement: Construction Method Statement - Clean Version - Revision 5.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum, Volume 3 Environmental Statement Addendum Appendices, Chapter 2 Main Development Site, Appendix 2.14.A: Water Monitoring and Response Strategy - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 6 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 2 Description of the Permanent Development Appendix 2B of the Environmental Statement: Lighting Management Plan - Tracked Changes Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.90 Draft Sabellaria Reef Management and Monitoring Plan - Tracked Changes Version - Version 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 3 MB)
Deadline 8 Submission - 9.98 Response to the ExA's Second Commentary on the draft DCO - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 23 MB)
Deadline 8 Submission - 2.10(B) Sizewell Link Road Plans for Approval 3 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 2 Description of the Permanent Development Appendix 2A of the Environmental Statement: Drainage Strategy - Tracked Changes Version - Revision 4.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site, Chapter 16 Terrestrial Historic Environment Appendix 16G of the Environment Statement: Peat Strategy - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 8.3(C) Associated Development Design Principles - Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 23 MB)
Deadline 8 Submission - 2.3(E) Work Plans Part 1 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.109 SZC Co. Response to Request for Further Information at Deadline 8 - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 13 MB)
Deadline 8 Submission - 8.3 A(B) Two Village Bypass Landscape and Ecology Management Plan Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 13 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Cooling Water Pumphouse and Associated Buildings Unit 2 Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 16 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Conventional Island (Unit 1) Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 9 MB)
Deadline 8 Submission - 9.35(A) Westleton Marsh Harrier Compensatory Habitat Strategy Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 4.1A(B) Statement of Reasons Appendix A Justification Tables
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.99 Comments on Earlier Deadlines and Subsequent Written Submissions to CAH1 and ISH8-ISH10
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.64 Draft Fen Meadow Plan - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 15 MB)
Deadline 8 Submission - 2.12(B) Green Rail Route Plans Not for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 8 MB)
Deadline 8 Submission - Environmental Statement Addendum Volume 3 Environmental Statement Addendum Appendices Chapter 2 Main Development Site Appendix 2.15.A: Coastal Processes Monitoring and Mitigation Plan - Tracked Changes Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 13 MB)
Deadline 8 Submission - 2.12(B) Green Rail Route Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 11 MB)
Deadline 8 Submission - 2.13 NDA Magnox Protective Provisions Access Road Plan
Other
NNB Generation Company (SZC) Limited (PDF, 47 MB)
Deadline 8 Submission - 2.3(F) Work Plans Part 2 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 10 MB)
Deadline 8 Submission - 2.5 Main Development Site Main Platform Proposed General Arrangement Plans (Operational) Plans Not for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 6 MB)
Deadline 8 Submission - 3.1(I) Draft DCO Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 6.19 Fifth Environmental Statement Addendum - Volume 2: Figures - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.105 Written Submissions responding to actions arising from Issue Specific Hearing 12: Community (15 September 2021)
Other
NNB Generation Company (SZC) Limited (PDF, 11 MB)
Deadline 8 Submission - 2.5(D) Main Development Site Highway Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 17 MB)
Deadline 8 Submission - 2.5(D) MDS Permanent Development Site Proposed Landscape Masterplan - Plans Not for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 11 MB)
Deadline 8 Submission - 9.88 Estate Wide Management Plan for the EDF Energy Estate - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 22 MB)
Deadline 8 Submission - 2.3(E) Work Plans Part 3 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 17 MB)
Deadline 8 Submission - 2.5 Main Development Site Highways Plans Not for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 19 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Nuclear Island Unit 2 Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.102 Written Summaries of Oral Submissions made at Issue Specific Hearing 13: Landscape, Visual Impact, Design and Terrestrial Heritage (16 September 2021) - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 9 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum, Volume 3 Environmental Statement Addendum Appendices Chapter 9 Rail Appendix 9.3.E: Draft Rail Noise Mitigation Plan - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 7 MB)
Deadline 8 Submission - 8.2(B) Outline Landscape and Ecology Management Plan - Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.10.23 Statement of Common Ground - Together Against Sizewell C - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.89 Draft Fish Impingement and Entrainment Monitoring Plan - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 3.2(H) Draft DCO Explanatory Memorandum Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.14 Updated National Policy Statement Tracker - Tracked Changes Version - Revision 5.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.107 Written Submissions responding to actions arising from Issue Specific Hearing 14: DCO, DoO and allied documents (17 September 2021)
Other
NNB Generation Company (SZC) Limited (PDF, 10 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Main Platform General Arrangement (Operational) Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 29 MB)
Deadline 8 Submission - 2.10(B) Sizewell Link Road Plans for Approval 2 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 17 MB)
Deadline 8 Submission - 2.5(C) Main Development Site Beach Landing Facility and SSSI Crossing Plans Part 2 of 2
Other
NNB Generation Company (SZC) Limited (PDF, 16 MB)
Deadline 8 Submission - 2.5(C) Main Development Site Operational Parameter Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 13 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum, Volume 3 Environmental Statement Addendum Appendices Chapter 9 Rail Appendix 9.3.E: Draft Rail Noise Mitigation Plan - Clean Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 4.1 C Updated Statement of Reasons Appendix C - Status of Negotiations with Statutory Undertakers - Revision 7.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.106 Written Submissions responding to actions arising from Issue Specific Hearing 13: Landscape, Visual Impact, Design and Terrestrial Heritage (16 September 2021)
Other
NNB Generation Company (SZC) Limited (PDF, 18 MB)
Deadline 8 Submission - 2.12(A) - Saxmundham to Leiston Branch Line Upgrades Existing Plans Not for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 6 MB)
Deadline 8 Submission - 6.13 Additional Ecology Survey Report (September 2021)
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum Volume 3 Environmental Statement Addendum Appendices Chapter 2 Main Development Site Appendix 2.11.A: Overarching Archaeological Written Scheme of Investigation - Tracked Changes Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 38 MB)
Deadline 8 Submission - 2.1(C) Land Plans
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 3.2(H) Draft DCO Explanatory Memorandum Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site, Chapter 3 Description of Construction, Appendix 3D of the Environmental Statement: Construction Method Statement - Tracked Changes Version - Revision 5.0
Other
NNB Generation Company (SZC) Limited (PDF, 3 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum Volume 3 Environmental Statement Addendum Appendices Chapter 2 Main Development Site Appendix 2.9.D: Fen Meadow Strategy - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 37 MB)
Deadline 8 Submission - 9.99 Comments on Earlier Deadlines and Subsequent Written Submissions to CAH1 and ISH8-ISH10 - Appendices Part 1 of 2 - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.110 Sizewell C European Sea Bass Stock Assessment - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.35(A) Westleton Marsh Harrier Compensatory Habitat Strategy Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 32 MB)
Deadline 8 Submission - 2.4(F) Rights of Way and Access Plans
Other
NNB Generation Company (SZC) Limited (PDF, 6 MB)
Deadline 8 Submission - 8.3 B(B) Sizewell Link Road Landscape and Ecology Management Plan - Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 4.1B Statement of Reasons Appendix B - Status of Negotiations with Owners of the Order Land - Revision 8.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.104 Written Submissions responding to actions arising from Issue Specific Hearing 11: Flooding, Water and Coastal Processes (14 September 2021)
Other
NNB Generation Company (SZC) Limited (PDF, 10 MB)
Deadline 8 Submission - 4.6 Updated Book of Reference and Schedule of Changes to the Book of Reference (BoR) - Revision 6.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.90 Draft Sabellaria Reef Management and Monitoring Plan - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 10 MB)
Deadline 8 Submission - 8.11(E) Code of Construction Practice Appendices Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 21 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Nuclear Island Unit 1 Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 25 MB)
Deadline 8 Submission - 8.3 B(B) Sizewell Link Road Landscape and Ecology Management Plan - Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 38 MB)
Deadline 8 Submission - 2.5(D) Main Development Site Landscape Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.88 Estate Wide Management Plan for the EDF Energy Estate - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 17 MB)
Deadline 8 Submission - 2.5(C) Main Development Site Beach Landing Facility and SSSI Crossing Plans Part 1 of 2
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 5.11(B) Schedule of Other Consents, Licences and Agreements Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 29 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 2 Description of the Permanent Development Appendix 2B of the Environmental Statement: Lighting Management Plan - Clean Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 7 MB)
Deadline 8 Submission -6.14 Environmental Statement Addendum Volume 3 Environmental Statement Addendum Appendices Chapter 2 Main Development Site Appendix 2.11.A: Overarching Archaeological Written Scheme of Investigation - Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 23 MB)
Deadline 8 Submission - 8.2(B) Outline Landscape and Ecology Management Plan - Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.14 Updated National Policy Statement Tracker - Tracked Changes Version - Revision 5.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 3.1(I) Draft DCO Tracked Changes Version- Revision 10 against Revision 9
Other
NNB Generation Company (SZC) Limited (PDF, 11 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 15 Amenity and Recreation Appendix 15I of the Environmental Statement: Rights of Way and Access Strategy - Clean Version -Revision 5.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.19 Fifth Environmental Statement Addendum - Volume 1: Main Text - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.101 Written Summaries of Oral Submissions made at Issue Specific Hearing 12: Community (15 September 2021)- Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 39 MB)
Deadline 8 Submission - 4.7 Land Plans showing Proposed Changes
Other
NNB Generation Company (SZC) Limited (PDF, 9 MB)
Deadline 8 Submission - 9.13 Sizewell C Coastal Defences Design Report
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.8 Wet Woodland Strategy - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 8.12 Updated Mitigation Route Map incorporating the amendments shown in the Mitigation Route Map Third Addendum Revision 1 - Revision 6.0
Other
NNB Generation Company (SZC) Limited (PDF, 7 MB)
Deadline 8 Submission - 9.4 Terrestrial Ecology Monitoring and Mitigation Plan - Clean Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 399 KB)
Deadline 8 Submission - Deadline 8 Cover Letter
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 15 Amenity and Recreation Appendix 15I of the Environmental Statement: Rights of Way and Access Strategy - Tracked Changes Version - Revision 5.0
Other
NNB Generation Company (SZC) Limited (PDF, 14 MB)
Deadline 8 Submission - 2.5(C) Main Development Site Rail Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Cooling Water Pumphouse and Associated Buildings Unit 1 Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 1.3 Updated Navigation Document - Revision 16.0
Other
NNB Generation Company (SZC) Limited (PDF, 38 MB)
Deadline 8 Submission - 8.17 Draft Deed of Obligation - Clean Version Part 2 of 2
Other
NNB Generation Company (SZC) Limited (PDF, 7 MB)
Deadline 8 Submission - 9.87 Draft Water Monitoring and Water Management Plan - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 16 MB)
Deadline 8 Submission - 2.5(A) Main Development Site Conventional Island (Unit 2) Plans for Approval
Other
NNB Generation Company (SZC) Limited (PDF, 28 MB)
Deadline 8 Submission - 9.64 Draft Fen Meadow Plan - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 8 MB)
Deadline 8 Submission - 9.108 Draft Wet Woodland Plan
Other
NNB Generation Company (SZC) Limited (PDF, 11 MB)
Deadline 8 Submission - 8.11(E) Code of Construction Practice Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.10.25 Statement of Common Ground - National Trust - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 9.11 Informal Recreation and Green Space Proposals - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum Volume 3 Environmental Statement Addendum Appendices Chapter 2 Main Development Site Appendix 2.15.A: Coastal Processes Monitoring and Mitigation Plan - Clean Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 22 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site Chapter 2 Description of the Permanent Development Appendix 2A of the Environmental Statement: Drainage Strategy - Clean Version - Revision 4.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site, Chapter 22 Marine Ecology and Fisheries Appendix 22N of the Environmental Statement: Marine Mammal Mitigation Protocol - Tracked Changes Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 41 MB)
Deadline 8 Submission - 4.3 Updated Book of Reference and Schedule of Changes to the Book of Reference (BoR) - Revision 7.0
Other
NNB Generation Company (SZC) Limited (PDF, 16 MB)
Deadline 8 Submission - 8.11(E) Code of Construction Practice Appendices Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 30 MB)
Deadline 8 Submission - 8.17 Draft Deed of Obligation - Clean Version - Part 1 of 2
Other
NNB Generation Company (SZC) Limited (PDF, 8 MB)
Deadline 8 Submission - 9.10.11 Statement of Common Ground - Royal Mail - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 29 MB)
Deadline 8 Submission - 2.10(B) Sizewell Link Road Plans Not for Approval 2 of 2
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site, Chapter 22 Marine Ecology and Fisheries Appendix 22N of the Environmental Statement: Marine Mammal Mitigation Protocol - Clean Version - Version 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.100 Written Summaries of Oral Submissions made at Issue Specific Hearing 11: Flooding, Water and Coastal Processes (14 September 2021) - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 9.65 Outline Vessel Management Plan - Tracked Changes Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.89 Draft Fish Impingement and Entrainment Monitoring Plan - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 5.10 Shadow Habitats Regulations Assessment Addendum - Appendix 9A(B) Southern North Sea Site Integrity Plan - Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 2.2(C) Crown Land Plans
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.103 Written Summaries of Oral Submissions made at Issue Specific Hearing 14: DCO, DoO and allied documents (17 September 2021) - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 8 MB)
Deadline 8 Submission - 9.87 Draft Water Monitoring and Management Plan - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.97 Responses to the ExA's Third Written Questions (ExQ3) Volume 1 - SZC Co. Responses - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 5.10 Shadow Habitats Regulations Assessment Addendum - Appendix 9A(B): Southern North Sea Site Integrity Plan - Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.10.7 Statement of Common Ground - Natural England
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.16 On-site Marsh Harrier Compensatory Habitat Strategy - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.97 Responses to the ExA's Third Written Questions (ExQ3) Volume 2 - Appendices - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission -9.96 Comments on Responses to the ExA's Second Written Questions (ExQ2) - Revision 1.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 8.11(E) Code of Construction Practice Clean Version
Other
NNB Generation Company (SZC) Limited (PDF, 12 MB)
Deadline 8 Submission - 6.3 Volume 2 Main Development Site, Chapter 16 Terrestrial Historic Environment Appendix 16G of the Environment Statement: Peat Strategy - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - Environmental Statement Addendum, Volume 3 Environmental Statement Addendum Appendices, Chapter 2 Main Development Site, Appendix 2.14.A: Water Monitoring and Response Strategy - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 8.3(C) Associated Development Design Principles - Tracked Changes Version
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 6.14 Environmental Statement Addendum Volume 3 Environmental Statement Addendum Appendices Chapter 2 Main Development Site Appendix 2.9.D: Fen Meadow Strategy - Tracked Changes Version - Revision 2 .0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.10.12 Statement of Common Ground - East Suffolk Council and Suffolk County Council - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 9.65 Outline Vessel Management Plan - Clean Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 6 MB)
Deadline 8 Submission - 9.16 On-site Marsh Harrier Compensatory Habitat Strategy - Clean Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 4 MB)
Deadline 8 Submission - 9.8 Wet Woodland Strategy - Tracked Changes Version - Revision 2.0
Other
NNB Generation Company (SZC) Limited (PDF, 7 MB)
Deadline 8 Submission - 9.4 Terrestrial Ecology Monitoring and Mitigation Plan - Tracked Changes Version - Revision 3.0
Other
NNB Generation Company (SZC) Limited (PDF, 36 MB)
Late Deadline 8 Submission (accepted at the discretion of the ExA) - 9.99 Comments on Earlier Deadlines and Subsequent Written Submissions to CAH1 and ISH8-ISH10 - Appendices Part 3 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 27 MB)
Late Deadline 8 Submission (accepted at the discretion of the ExA) - 9.99 Comments on Earlier Deadlines and Subsequent Written Submissions to CAH1 and ISH8-ISH10 - Appendices Part 2 of 3
Other
NNB Generation Company (SZC) Limited (PDF, 36 MB)
Deadline 8 Submission - 8.17 Draft Deed of Obligation - Appendix A - Plans - Revision 7.0
Other
NNB Generation Company (SZC) Limited (PDF, 5 MB)
Deadline 8 Submission - 8.17 Draft Deed of Obligation - Tracked Changes Version - Revision 8.0
Other
Walker Morris LLP on behalf of Northumbrian Water Limited (PDF, 110 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Office for Nuclear Regulation (PDF, 198 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Patricia O'Connor (PDF, 95 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Paul Collins (PDF, 88 KB)
Deadline 8 Submission
Other
Paul Taylor (PDF, 128 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Peter Wagstaff (PDF, 154 KB)
Deadline 8 Submission
Other
Philip Smith (PDF, 177 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Richard Nichols (PDF, 83 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Robert Brock (PDF, 204 KB)
Deadline 8 Submission
Other
Rose Hart (PDF, 111 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Royal Society for the Protection of Birds (RSPB) (PDF, 308 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Royal Society for the Protection of Birds (RSPB) (PDF, 251 KB)
Deadline 8 Submission - Responses to Change 19 Request
Other
Royal Society for the Protection of Birds (RSPB) (PDF, 280 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Royal Society for the Protection of Birds (RSPB) (PDF, 2 MB)
Deadline 8 Submission - Cover Email
Other
Royal Society for the Protection of Birds (RSPB) (PDF, 652 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
Rt Hon Dr Thérèse Coffey MP (PDF, 1 MB)
Deadline 8 Submission - Responses to Change Request 19
Other
Regan Scott on behalf of S.A.G.E (PDF, 378 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - oral summary and associated comments for ISH12 and 13
Other
Regan Scott on behalf of S.A.G.E (PDF, 138 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Sally Ilett (PDF, 79 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Sarah Muir Poland (PDF, 89 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Sarah T Chandler (PDF, 121 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Simon Ilett (PDF, 80 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Simon Mellen (PDF, 3 MB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
NNB Generation Company (SZC) Limited on behalf of Sizewell C Project (PDF, 4 MB)
Deadline 8 Submission - 8.3 A(B) Two Village Bypass Landscape and Ecology Management Plan Tracked Changes Version
Other
Snape Parish Council (PDF, 129 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Stephen Beaumont (PDF, 96 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Suffolk Coast & Heaths Area of Outstanding Natural Beauty (AONB) (PDF, 98 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case - Issue Specific Hearing 12
Other
Suffolk Coast & Heaths Area of Outstanding Natural Beauty (AONB) (PDF, 126 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case - Issue Specific Hearing 13
Other
Suffolk Coast and Heaths Area of Outstanding Natural Beauty (AONB) Partnership (PDF, 154 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Suffolk Coastal Friends of the Earth (PDF, 191 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case - Water Management Strategy
Other
Suffolk Coastal Friends of the Earth (PDF, 230 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case - Expert Comments on ISH11
Other
Suffolk Constabulary (PDF, 305 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Written summaries of oral statements made at Issue Specific Hearings 12 and 14
Other
Suffolk Constabulary (PDF, 99 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Cover Letter
Other
Stantec UK Ltd on behalf of Suffolk Constabulary (PDF, 290 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Stantec UK Ltd on behalf of Suffolk Constabulary (PDF, 105 KB)
Deadline 8 Submission - Cover Letter
Other
Suffolk County Council (PDF, 150 KB)
Deadline 8 Submission - Overview Letter
Other
Suffolk County Council (PDF, 1 MB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
Suffolk County Council (PDF, 253 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 13 (16 September 2021) – (ISH13) Landscape and Historic Heritage
Other
Suffolk County Council (PDF, 315 KB)
Deadline 8 Submission - Responses to the ExA’s third Written Questions (ExQ3)
Other
Suffolk County Council (PDF, 181 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
Suffolk County Council (PDF, 572 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 11 (14 September 2021) – (ISH11) Flooding, Water and Coastal Processes
Other
Suffolk County Council (PDF, 255 KB)
Deadline 8 Submission - Responses to ExA’s commentary on, or proposed schedule of changes to, the draft DCO and s.106 documentation
Other
Suffolk County Council (PDF, 474 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 12 (15 September 2021) – (ISH12) Community
Other
Suffolk County Council (PDF, 415 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 14 (17 September 2021) – (ISH14) DCO, Code of Construction Practice and similar regulatory documents, Deed of Obligation, reasonable endeavours
Other
Suffolk County Council (PDF, 297 KB)
Deadline 8 Submission - Other: Attendance list for ISH15
Other
Susan Morrice (PDF, 170 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Sylvia Ballard (PDF, 349 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISSUE SPECIFIC HEARING 12 – SESSION 3 Section 4 ii re: BRIDLEWAY 19 LEISTON CUM SIZEWELL
Other
The Heveningham Hall Estate (PDF, 329 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - The Setting of Heritage Assets
Other
The Heveningham Hall Estate (PDF, 52 MB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Yoxford Conservation Area Appraisal February 2020
Other
The Heveningham Hall Estate (PDF, 401 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISH13 LANDSCAPE, VISUAL IMPACT AND TERRESTRIAL HERITAGE
Other
The Heveningham Hall Estate (PDF, 967 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
The Suffolk Coast Destination Management Organisation Ltd (TSC) (PDF, 204 KB)
Deadline 8 Submission
Other
Theberton and Eastbridge Parish Council (PDF, 207 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Theberton and Eastbridge Parish Council (PDF, 211 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 14 (ISH14) on Development Consent Order, Deed of Obligation and allied documents.
Other
Theberton and Eastbridge Parish Council (PDF, 40 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 12 (ISH12) on Community, Amenity and Recreational, Human Health
Other
Theberton and Eastbridge Parish Council (PDF, 98 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 13 (ISH13) Landscape, Visual Impact, Design and Terrestrial Heritage
Other
Theberton and Eastbridge Parish Council, Stop Sizewell C and Minsmere Levels Stakeholders Group (PDF, 448 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Tina Gaudoin (PDF, 141 KB)
Deadline 8 Submission
Other
Together Against Sizewell C (TASC) (PDF, 282 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Together Against Sizewell C (TASC) (PDF, 377 KB)
Deadline 8 Submission - Responses to Change Request 19 - PROPOSAL FOR DESALINATION PLANT
Other
Together Against Sizewell C (TASC) (PDF, 300 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Dr Henderson's review of the Applicant's marine documents 9.67 and 9.70
Other
Together Against Sizewell C (TASC) (PDF, 187 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISH10 ECOLOGY
Other
Together Against Sizewell C (TASC) (PDF, 285 KB)
Deadline 8 Submission - Comments on any additional information/submissions received by D7
Other
Together Against Sizewell C (TASC) (PDF, 224 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case
Other
Together Against Sizewell C (TASC) (PDF, 280 KB)
Deadline 8 Submission - Post hearing submissions including written submissions of oral case - ISH12 Community Impacts
Other
Together Against Sizewell C (TASC) (PDF, 170 KB)
Deadline 8 Submission - ORAL REPRESENTATIONS & COMMENTS REGARDING ISH13 LANDSCAPE, VISUAL IMPACT, DESIGN & TERRESTRIAL HERITAGE
Other
Together Against Sizewell C (TASC) (PDF, 1 MB)
Deadline 8 Submission - ORAL REPRESENTATIONS & COMMENTS REGARDING ISH 11 FLOODING, WATER & COASTAL PROCESSES
Other
Tom Brent (PDF, 135 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Tracey Gardiner (PDF, 113 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Vanessa Tucker (PDF, 23 KB)
Deadline 8 Submission - Accepted at the discretion of the Examining Authority
Other
Viv Mason (PDF, 98 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Cllr Josie Bassinette on behalf of Walberswick Parish Council (PDF, 115 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Wayne Jones (PDF, 360 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Westleton Parish Council (PDF, 209 KB)
Deadline 8 Submission - Responses to Change Request 19
Other
Wickham Market Parish Council (PDF, 8 MB)
Deadline 8 Submission - Other: Wickham Market Update on SP&R Landscape and WM Traffic Matters
Other
Richard Cooper on behalf of Wickham Market Parish Council, Hacheston Parish Council, Marlesford Parish Council and Campsea Ashe Parish Council (PDF, 2 MB)
Deadline 8 Submission
Other
Woodbridge Town Council (PDF, 153 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Woodbridge Town Council (PDF, 142 KB)
Deadline 8 Submission - Responses to any further information requested by the ExA for this deadline
Other
Yoxford Parish Council (PDF, 397 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case
Other
Yoxford Parish Council (PDF, 171 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - Issue Specific Hearing 11
Other
Yoxford Parish Council (PDF, 149 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISSUE SPECIFIC HEARING (ISH) 12 ON WEDNESDAY 15 SEPTEMBER 2021
Other
Yoxford Parish Council (PDF, 83 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case - ISSUE SPECIFIC HEARING (ISH) 13 ON THURSDAY 16 SEPTEMBER 2021
Other
Yoxford Parish Council (PDF, 540 KB)
Deadline 8 Submission - Post Hearing submissions including written submissions of oral case