Lake Lothing Third Crossing

What happens next

Dates for the Examination can be viewed on the Examination Timetable page.

Notice of the Procedural Decision has been issued by the Examining Authority to Interested Parties in the Rule 8 letter; this includes information about how the Examination will be conducted and the Examination Timetable as currently set out.

05/06/2019 - Deadline for close of examination. See the Examination Timetable for further information.

If you have a legal interest in land affected by a Nationally Significant Infrastructure Project and:

  • have not been identified by the Applicant; and
  • did not register to become an Interested Party;

then you can make a request to the Examining Authority to become an Interested Party under s102A of the Planning Act 2008.

Timeline (11 items)

milestone icon Read the letter

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties

Procedural decision following Preliminary Meeting

17 December 2018
milestone icon
  • Preliminary Meeting takes place
  • Examination begins
05 December 2018
milestone icon

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

06 November 2018
milestone icon
Relevant representations published on the website
10 October 2018
milestone icon
Registration of interested parties closes
24 September 2018
milestone icon
Registration of interested parties begins
17 August 2018
notice icon

The application has been accepted for examination. View the acceptance letter.

09 August 2018
milestone icon Read the letter

The application has been accepted for examination

09 August 2018
milestone icon
Decision on whether or not to accept the application for examination
09 August 2018
notice icon

This application was received by the Planning Inspectorate on 13 July 2018.

The application documents will be made available if the application is accepted for examination.

It is for the Applicant to decide whether or not application documents can be published upon submission (see government guidance).

13 July 2018
milestone icon
Application received by the Planning Inspectorate
13 July 2018