Hornsea Project Three Offshore Wind Farm

You can filter the results to show only the items that match your interest.

Date

SourceDescription
Other
Size: 2 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Post hearing submission
Other
Size: 208 KB
South Norfolk Council, North Norfolk District Council and Broadland District Council
Deadline 6 Submission - Revised version of the applicant’s Outline Landscape Plan requested by the Examining Authority
Other
Size: 15 KB
Helen & Chris Monk
Deadline 6 Submission - Suggested Location for Accompanied Site Inspection - Accepted at the discretion of the Examining Authority
Other
Size: 10 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission -Revised Draft Development Consent Order - Clean
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Statement of Commonality of Statements of Common Ground (SoCG)
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Written summary of Applicant’s oral case put at Issue Specific Hearing 6 (30th Jan 2019)
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Statement of Common Ground between Hornsea Project Three and the NFFO and VisNed
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Written summary of Applicant’s oral case put at Issue Specific Hearing 5 (29th Jan 2019)
Other
Size: 48 KB
Oulton Parish Council
Deadline 6 Submission - Response to Deadline 6
Other
Size: 20 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 25 - Hornsea Three and Norfolk Vanguard Cumulative Link Impact Assessment Relating to Traffic
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Guide to the Application
Other
Size: 9 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Schedule of Changes - Development Consent Order and Deemed Marine Licences
Other
Size: 6 MB
The Royal Society for the Protection of Birds
Deadline 6 Submission - Appendix 3.2 - Collision Risk Modelling: update and clarification
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Written summary of Applicant’s oral case put at Compulsory Acquisition Hearing (31st Jan 2019)
Other
Size: 3 MB
The Royal Society for the Protection of Birds
Deadline 6 Submission - Written Submission
Other
Size: 58 KB
Weybourne Parish Council
Deadline 6 Submission - Response to Deadline 6
Other
Size: 283 KB
The Wildlife Trusts
Deadline 6 Submission - Post-hearing submission and further comments
Other
Size: 9 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Revised Draft Development Consent Order – Tracked Changes
Other
Size: 447 KB
Trinity House
Deadline 6 Submission - Written Representation for Issue Specific Hearing 6 - Draft Development Consent Order
Other
Size: 12 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 5 - Comments on Condition Assessment for The Wash and North Norfolk Coast SAC
Other
Size: 14 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 7 - Johnson and Cook 2016
Other
Size: 12 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 6 - Offshore ornithology Hearing Clarifications-cumulative and in combination assessment methods and age class data
Other
Size: 14 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 31 - CIGRE Report 2009 - Service Experience of HV Underground and Submarine Cable Systems
Other
Size: 16 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 8 -Smart Wind and Forewind 2014 Report
Other
Size: 1 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Application for Non-material amendments including Additional Land
Other
Size: 27 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 3a - Annex A - Hornsea Three Highway Intervention Schemes (The Street)
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Cover Letter
Other
Size: 13 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 30 - Outline Onshore Written Scheme of Investigation
Other
Size: 15 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 3b - Annex A - Hornsea Three Highway Intervention Schemes
Other
Size: 14 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 9 - Trinder M., 2017
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Commentary on progress made with Spirit Energy at Deadline 6
Other
Size: 14 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 4 - Rock Protection Decommissioning Methods
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Applicant's comments on Written Representations and Responses submitted by Interested Parties at Deadline 5
Other
Size: 14 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 21 - Brassuer et al., 2015
Other
Size: 13 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 28 - Position of the Applicant in relation to collision risk modelling
Other
Size: 16 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 26 - Outline Ecological Management Plan
Other
Size: 13 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 29 - Applicants interpretation of Natural England’s position in relation to collision risk modelling
Other
Size: 21 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 24 - Proposed Use of Temporary Working Areas for Micrositing - Implications for Environmental Statement
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 22 - Marine Mammal Hearing Clarifications
Other
Size: 13 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 27 - Forsythe et al., 1995
Other
Size: 9 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 3 - Outline Construction Traffic Management Plan
Other
Size: 10 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 20 - Graham et al., 2018
Other
Size: 9 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 2 - Outline Code of Construction Practice
Other
Size: 7 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 19 - Alerstam et al., 2007
Other
Size: 8 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 23 - Construction Traffic Noise and Vibration Assessment at The Old Railway Gatehouse
Other
Size: 622 KB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 17 - Garthe et al., 1999
Other
Size: 10 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 13 - Ornithology roadmap with Natural England for the examination phase (ver.C)
Other
Size: 167 KB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 18 - Duant et al 2002
Other
Size: 9 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 1 -Clarification Note on Onshore Cable Corridor Widths (HVAC and HVDC)
Other
Size: 18 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 11 - Aitken et al., 2014
Other
Size: 10 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 15 - Pennycuick 1997
Other
Size: 9 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 16 - Johnston et al., 2014 with Corrigendum
Other
Size: 15 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 12 - Preliminary Trenching Assessment
Other
Size: 3 MB
Natural England
Deadline 6 Submission - Written summary of Representations made at ISH6 DCO Hearing
Other
Size: 3 MB
North Norfolk District Council
Deadline 6 Submission - Post hearing submission - Issue Specific Hearing on 30 January 2019
Other
Size: 39 KB
Addleshaw Goddard LLP on behalf of Network Rail
Deadline 6 Submission - Response to Item 11(c) of the Agenda
Other
Size: 11 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 14 - Warwick-Evans et al., 2018
Other
Size: 12 MB
Ørsted Hornsea Project Three (UK) Ltd
Deadline 6 Submission - Appendix 10 -Horsewill and Robinson 2015
Other
Size: 3 MB
Natural England
Deadline 6 Submission - ISH6 Annex B- Natural England’s Comments on REP4-023 Code of Construction Practice Rev.2
Other
Size: 2 MB
Natural England
Deadline 6 Submission - ISH 5 Annex D- Natural England Comments on REP4-012 pg 43 onwards Applicants response to ExA Q2.2.46 in relation to MEEB.
Other
Size: 3 MB
Natural England
Deadline 6 Submission - Written Submission of Representations at Issue Specific Hearing 5 - Offshore Ecology
Other
Size: 3 MB
Natural England
Deadline 6 Submission - ISH6 Annex A -Natural England’s Comments on the Applicant’s Proposed DML appeal conditions
Other
Size: 41 KB
DLA Piper UK LLP on behalf of National Grid
Deadline 6 Submission - Response to Deadline 6
Other
Size: 3 MB
Natural England
Deadline 6 Submission - ISH 5 Appendix C- Natural England Comments on REP5 – 011- Appendix 3 Cable Specification Installation Plan (CSIP)
Other
Size: 2 MB
Natural England
Deadline 6 Submission - ISH5 Annex F - Natural England’s Response to the Applicant’s response to ExA Q2.2.25
Other
Size: 2 MB
Natural England
Deadline 6 Submission - ISH 5 Annex E- Natural England’s comments on REP3 – 024 Appendix 15 The Wash and North Norfolk Coast (W&NNC) SAC In-combination Assessment
Other
Size: 3 MB
Natural England
Deadline 6 Submission - ISH 5 Annex B - Natural England’s comments on REP5 – 010 Preliminary Trenching Assessment (PTA)
Other
Size: 2 MB
Natural England
Deadline 6 Submission - ISH5 Annex A - Natural England’s Comments on REP 4-097 Biotope Clarification paper as requested at ISH 5
Other
Size: 3 MB
Natural England
Deadline 6 Submission - ISH5 Annex G- Natural England’s Comments on the Applicant’s response to ExA Q2.2.38
Other
Size: 2 MB
Natural England
Deadline 6 Submission - ISH 5 Annex H - Natural England’s Response to REP5-014
Other
Size: 2 MB
Marine Management Organisation
Deadline 6 Submission - Post hearing submissions including written submissions of oral cases
Other
Size: 887 KB
National Farmers Union And The Land Interest Group
Deadline 6 Submission - Written submission - Issue Specific Hearing – Draft Development Consent Order - Wednesday 30th January 2019
Other
Size: 145 KB
N2RS
Deadline 6 Submission - Concerns about Public Engagement and Observations on the Current Project Design
Other
Size: 64 KB
N2RS
Deadline 6 Submission - Post hearing submissions including written submissions of oral cases
Other
Size: 975 KB
National Farmers Union And The Land Interest Group
Deadline 6 Submission - Written submission - Issue Specific Hearing - Compulsory Acquisition - Thursday 31st January 2019
Other
Size: 5 MB
Mulbarton Parish Council
Deadline 6 Submission - Response to Deadline 6
Other
Size: 1,008 KB
Bidwells LLP on behalf of Mr Kemp
Deadline 6 Submission - Post hearing submission
Other
Size: 303 KB
Historic England
Deadline 6 Submission - Post hearing submissions including written submissions of oral cases
Other
Size: 44 KB
DLA Piper UK LLP on behalf of Cadent Gas Limited
Deadline 6 Submission - Response to Deadline 6
Other
Size: 135 KB
N2RS
Deadline 6 Submission - Local cumulative environmental impact assessments of the cable route on landscape, tourism, traffic and recreation
Other
Size: 2 MB
Marine Management Organisation
Deadline 6 Submission - Written Representation
Other
Size: 803 KB
Maritime & Coastguard Agency
Deadline 6 Submission - Report following aviation trials and exercises in relation to offshore wind farms
Other
Size: 951 KB
Maritime & Coastguard Agency
Deadline 6 Submission - Responses to the applicants comments on representations made by Maritime & Coastguard Agency at deadline 4.