East Anglia THREE Offshore Wind Farm

Enquiry received via email

East Anglia THREE Offshore Wind Farm

05 August 2013
East Anglia Offshore Wind - Keith Morrison

Enquiry

EAOL set out the draft timetable for consultation and sought views from the Planning Inspectorate.

Advice given

Thank you for your email detailing your approach to consultation. This approach appears to be inline with previous advice given on this case. The timeline does not explicitly mention submitting a s46 notification, this must be received by the Secretary of State on or before you commence s42 consultation. Furthermore, the time period for consulting the Local Authorities on the content of the Statement of Community Consultation appears to falls wholly within the month of August. The Planning Inspectorate advises that you may wish to consider the implications of this.