East Anglia ONE Offshore Windfarm

What happens next

A decision on the application for a Development Consent Order for East Anglia ONE Offshore Windfarm was taken on 17 June 2014.

Timeline (16 items)

A Decision Letter (PDF, 325KB) and Amendment Order (PDF, 354KB) have been issued by the Department for Business, Energy and Industrial Strategy to make a change that is not material to the East Anglia ONE Offshore Wind Farm Order 2014.

24 September 2021

Representations received in response to the application for a non-material change to the East Anglia ONE Offshore Windfarm Development Consent Order have been published.

08 June 2021

An application for a non-material change to the East Anglia ONE Offshore Windfarm Development Consent Order has been made by East Anglia One Ltd. If you wish to make a representation, this should be emailed to [email protected].

As a result of ongoing Government guidance relating to the Coronavirus (COVID-19), the Planning Inspectorate’s office based at Temple Quay House is now closed and any submissions sent by post may be subject to delay. If you have difficulty in submitting a representation by email, please contact [email protected] or 0303 444 5000 and a member of the Planning Inspectorate’s case team will be able to assist.

Following a request by Natural England, the Secretary of State has agreed to extend the deadline for receipt of representations until 4 June 2021.

25 May 2021

An application for a non-material change to the East Anglia ONE Offshore Windfarm Development Consent Order has been made by East Anglia One Ltd. If you wish to make a representation, this should be emailed to [email protected].

As a result of ongoing Government guidance relating to the Coronavirus (COVID-19), the Planning Inspectorate’s office based at Temple Quay House is now closed and any submissions sent by post may be subject to delay. If you have difficulty in submitting a representation by email, please contact [email protected] or 0303 444 5000 and a member of the Planning Inspectorate’s case team will be able to assist.

The deadline for receipt of representations is 25 May 2021.

07 April 2021

The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

29 January 2020
Decision made by the Secretary of State
17 June 2014
Recommendations given by the Planning Inspectorate
18 March 2014
Examination ends

23 December 2013
  • Preliminary Meeting takes place
  • Examination begins
25 June 2013
Relevant representations published on the website
11 March 2013
Registration of interested parties closes
07 March 2013
Registration of interested parties begins
25 January 2013
Decision on whether or not to accept the application for examination
14 December 2012
Application received by the Planning Inspectorate
21 November 2012
Application expected from applicant
19 November 2012