There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

The London Resort

26 February 2018
Bramwell Associates - Dan Bramwell

Enquiry

The enquirer represented the Peninsula Management Group; the organisation that represents the 140 businesses on the Northfleet Industrial Estates.
The enquirer queried the accuracy of the anticipated submission dated provided on the National Infrastructure Planning website; whether the Inspectorate had any future meetings planned with London Resort Company Holdings (LRCH); and whether LRCH would be undertaking public consultations about any plans to carry out works to junctions on the A2.

Advice given

As you are likely aware from the advice register on our website, we have had no substantive contact with LRCH since August 2017. A project update meeting between the Planning Inspectorate and LRCH is however scheduled in March 2018. As required, a note of the meeting will be published to our website shortly afterward.
The situation in respect of how the LRCH and Highways England schemes might interrelate is complex, and the Planning Inspectorate hopes to learn further how LRCH intends to progress in this regard at the March meeting. We will also expect an update in respect of LRCH’s Pre-application programme (ie timescales). If, as we currently understand, LRCH intends to include works to the A2 in its Development Consent Order, it will be required to consult on those works in its public consultation.