The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

Medworth Energy from Waste Combined Heat and Power Facility View all advice for this project

25 March 2022
WisWIN - Tom Howlett

Enquiry

We are anxiously awaiting MVV submission concerning their EfW proposal for Algores Way, Wisbech. Cambs. As part of the planning process the submission enters a phase called Pre-application, where the said proposal is considered for acceptance. The time scale for this process is stated as 28 days. Could you confirm if this process is purely a box tick phase, or internal consideration, or does anybody visit Wisbech from planning dept.? Thanks for your comments.

Advice given

Thank you for your email and please accept my apologies for the delay in replying. In response to your query regarding the Acceptance of Medworth Energy from Waste Combined Heat and Power Facility, a Nationally Significant Infrastructure Project, I would like to draw your attention to the following information. To help decision-making on whether or not applications are of a satisfactory standard to be accepted for examination, the Planning Inspectorate has produced an ‘Acceptance of Applications Checklist’ based upon the criteria set out in s55 of the Planning Act 2008. A copy of the checklist is provided at Appendix 3 of Advice Note 6. Please note that the completion of this checklist by the Applicant should not however be seen as a guarantee that the application will be accepted as this is a matter for the Planning Inspectorate to consider on behalf of the Secretary of State. For further information please follow the links below; attachment 1 attachment 2 I hope you find the above information useful.


attachment 1
attachment 1
attachment 2
attachment 2