The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via post

Dogger Bank Teesside A / Sofia Offshore Wind Farm (formerly Dogger Bank Teesside B) - Project previously known as Dogger Bank Teesside A&B

15 August 2014
Savills on behalf of Airvolution - David Palmer

Enquiry

Letter dated 30 July 2014 published on our website on 15 August 2014

Advice given

Thank you for your letter of 30 July 2014 which was received in this office on 6 August
2014.
The Examining Authority (ExA) has accepted this into the examination and it will be
made available on the website page for this project as an examination document.
You may wish to note that, as your client Airvolution Energy Ltd are in the Book of
Reference, they are an interested party and an affected person giving them rights to
participate in the process including receiving examination correspondence and an
entitlement to be heard at a compulsory acquisition hearing and an open floor
hearing. It will be for you and your client to consider whether your client wishes to
take an active part in the examination. Should you wish to proceed on this basis, I
would recommend you submit any written representations and/or requests to be
heard at a compulsory acquisition hearing or any other event as set out in the
timetable by Deadline III (3 September). Copies will then be forwarded to the ExA for
their consideration.
The Rule 8 letter which was sent to your client, includes the examination timetable
was published on Monday 11 August 2014 and can be accessed at the following link;
attachment 1
ipc/uploads/projects/EN010051/2.%20Post-Submission/Procedural%20Decisions/Rule%208%20Letter.pdf
You may also wish to note on this page is the option to sign up to be notified of
updates on the project. To do this, you will need to input your email address into the
box under ?Email Updates? and click ?sign up?. This will take you to a new screen where
you need to input your name, confirm your email address again and click in the tick
box for ?All updates?
Further information about the process is available in the following advice notes:
attachment 2
8-1v4.pdf
attachment 2
8-5v3.pdf
If you have any further queries, please don?t hesitate to contact me.