Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Rail Central (Strategic Rail Freight Interchange)

11 September 2018
Mark Redding

Enquiry

In a planning meeting with the Developer on the 25th May the Inspectorate stated the following:
'The Inspectorate noted that two Examinations running simultaneously was likely to put some strain on NR’s resources. The Inspectorate requested that the Applicant provide the contact details for NR in order for the Inspectorate to have an unbiased discussion with NR about the two schemes. The Inspectorate also noted that the examination of both schemes would involve the same Local Authorities (LAs) and other stakeholders and highlighted that the examination of just one proposal can put a strain on the resources of these persons/organisations.'
In July I formally asked whether or not this had been done but had no reply. On the 28th August I followed up on the phone to be told that this conversation had not taken place (and would most likely not). Would it be possible to publish this query on the web site and then provide the reason as to why it has not when it was specifically requested by yourselves.
This is not a side issue, it is absolutely critical for the whole of the area and local community so I am disappointed that nothing further has happened. I am beginning to wonder at what stage this absolutely critical issue will be addressed. Nobody seems willing to adopt a pro-active approach.

Advice given

As you may now be aware, the Rail Central Strategic Rail Freight Interchange (SRFI) application is due to be submitted in mid-September 2018. As a result, the level of overlap of the examination stages for both projects (if the Rail Central application is accepted for examination) will be less than initially anticipated, however we note that an overlap towards the latter part of the Northampton Gateway SRFI examination and the start of the Rail Central SRFI examination is still likely.
Whilst it is ultimately for the relevant appointed Examining Authority to determine how to examine each application, there are opportunities for you to have your say on the examination process at the Preliminary Meetings for each project. In addition, as the Northampton Gateway SRFI examination timetable will be finalised by the point at which the Rail Central SRFI draft examination timetable will be produced, efforts will be made to avoid deadline and hearing date clashes where possible.
We held a telecon meeting with Network Rail today to discuss the Planning Act 2008 process, a meeting note will be published on our website in due course.
In regard to the information we publish on our website, The Planning Inspectorate is required to publish advice it provides under section 51 of the Planning Act 2008 which relates to:
- applying for an order granting development consent; or
- making representations about an application, or a proposed application, for such an order.
I hope you find the above information to be helpful.