The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.
There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.
Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.
Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.
Triton Knoll Electrical System View all advice for this project
Enquiry
The applicant has agreed to certain wording in respect to the clearance under watercourses to be included in the Construction Method Statement. The version of the CMS submitted for deadline 6 did not include the agreed wording. This error has been flagged up to the applicant who has stated that it will be corrected.
If a revised CMS is submitted for deadline 7 will it be published online and will there be an opportunity for comment should the agreed wording be absent?
Advice given
Dear Mr Carrott,
Any deadline documents received for deadline 7 will be available to view on the project webpage as soon as practicable after the close of the deadline. The Examining Authority has just issued a Rule 17 in which they have added an additional deadline on Monday 29 February 2016. This deadline is for any comments on documents received at Deadline 6 and 7.