Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via phone

Sheringham and Dudgeon Extension Projects View all advice for this project

31 October 2019
Oulton Parish Council - Alison Shaw

Enquiry

1) How are consultees, particularly Parish Councils, identified for notification and consultation on the Scoping Report? Who identifies them? 2) Can Parish Councils that are not consulted by PINS comment on the Scoping Report? 3) Will the bodies that were notified and consulted be informed when the Scoping Opinion is adopted?

Advice given

1) The Planning Inspectorate identifies consultation bodies in accordance with legislation (Schedule 1 of The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009). Any parish council within which the Proposed Development would be located (ie the ‘scoping area’ identified in the Scoping Report) would be notified and consulted. A list of all consultation bodies will be included in the Scoping Opinion, once adopted. 2) Only responses received from consultation bodies that were notified and consulted will be included in the Scoping Opinion. If a Parish Council that has not been notified and consulted wishes to comment on the Scoping Report, it is recommended that they send their comments directly to the applicant. 3) The Inspectorate has 42 days from receipt of a scoping request to adopt a Scoping Opinion and will publish it on the project page of the website. Consultation bodies will not be individually notified of its publication.