There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.
Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.
Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.
A47 Blofield to North Burlingham View all advice for this project
Enquiry
I've recently joined Anglian Water and identified that Anglian hasn't submitted Relevant Representations for the A47 Blofeld or the Tuddenham scheme. I've agreed with Highways England Programme lead that Anglian will seek a dispensation to submit Relevants Reps to ensure these matters are before the Examining Authority. Can you advise on the address to send the Reps to for Blofield and for Tuddenham?
Advice given
The deadline for ‘Relevant Representations’ (RRs) (preliminary submissions setting out the matters that are to be raised in more detail at Examination) for the A47 Blofield to North Burlingham project elapsed on 6 April 2021. However, as a Statutory Consultee, Anglian Water can participate at the Examination and submit written submissions to update the Examining Authority on its position in respect of the Proposed Development without needing to register and provide a RR. As the Examination has commenced, the deadline for ‘Written Representations’ (WRs), your comprehensive written submission, is Deadline 2 - 20 July 2021. You can either submit your WR via email ([email protected]) or via the project page’s portal on the following link: attachment 1;d=Deadline+2+D2 In respect of the A47 North Tuddenham to Easton application, the RR deadline has also elapsed. However, once Examination commences, you will have the same opportunity to provide a WR for the Proposed Development to set out Anglian Water’s position and raise any pertinent matters. The ‘Rule 6’ letter, which amongst other things invites attendance to the Preliminary Meeting and circulates the draft Examination Timetable, includes a cursory date of Deadline 1 – 1 September 2021 for WRs (tbc). You can provide your WR via the project’s email ([email protected]) or via the project’s portal once live following the commencement of the Examination.