There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

West Midlands Interchange View all advice for this project

16 October 2017
Mary Jones

Enquiry

As a local resident of South Staffordshire, we are at present campaigning against the proposed West Midland Strategic Rail Freight Interchange (WM SFRI)
We have had public consultations with the developers where we have expressed our opinions and opposition to this proposal, on many issues.
One of the issues being the development on 700 acres of Green Belt land, and the impact this will have on the Wildlife and destruction of Mature Trees.
I urge you to look into your governments policies regarding Green Belt and the Natural Environment and Rural communities, with regard to this matter.

Advice given

At present this proposed development is in the Pre-Application stage of the planning process for nationally significant infrastructure projects (NSIPs); during this stage the developer will be preparing their application documents to be submitted to us, as well as consulting with the local community on their proposals. At this stage the application has not been finalised, and as such we advise for any concerns related to the project to be submitted directly to the developer, in order for your views to inform the application before the final version is submitted to us for consideration.
The contact information for the developer is as follows:
[email protected]
tel. 0800 377 7345
We also advise you to contact the relevant local authority with any concerns, as they are required to submit a report to us on the consultation activities undertaken by the Applicant during the Pre-Application stage once the application for the project has been submitted.
If the application is submitted and accepted by us, the appointed Examining Authority is required to take the relevant National Policy Statement into consideration, along with any other relevant policies as part of their Examination of the application prior to submitting their recommendation to the Secretary of State.
I have attached a copy of our Advice Note: Overview of the nationally significant infrastructure planning process for members of the public, which I hope you will find helpful. Please also refer to our website for further information.