Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

Norfolk Vanguard View all advice for this project

19 July 2018
Jenny Smedley

Enquiry

The enquirer submitted representations regarding the merits of the proposed development to the Planning Inspectorate.

Advice given

The application was submitted to Planning Inspectorate on 26 June 2018. Beginning on the day after it was submitted the Planning Inspectorate (on behalf of the Secretary of State) has 28 calendar days to decide whether the application can be accepted for examination.
The Acceptance decision must therefore be taken on or before 24 July 2018. The decision will be published on the project webpage, here:
attachment 1
If the application is accepted, the following documents will also be published on the project webpage:
• Any Adequacy of Consultation Representations submitted by relevant local authorities.
• The Planning Inspectorate’s Acceptance Checklist.
The Acceptance tests
Section 55 of the Planning Act 2008 (PA2008) states what the Planning Inspectorate, on behalf of the Secretary of State, must have regard to when taking its decision about whether to accept an application:
a) The Consultation Report received with the application.
b) Any Adequacy of Consultation Representations received by the Planning Inspectorate from a local authority consultee.
c) The extent to which the Applicant has had regard to government guidance.
Comments about the merits of the Proposed Development (eg setting out support for or objection to the principle of the Proposed Development) cannot be considered at the Acceptance stage. If the application is accepted for examination, in order to make comments about the merits of the Proposed Development to an appointed Examining Authority, you will need to register as an Interested Party by making a Relevant Representation at the appropriate time. For more information about how and when you can have your say, please see our Advice Note 8.2: How to register to participate in an Examination: attachment 2
Once registered as an Interested Party, you will be invited to: attend the Preliminary Meeting, attend any scheduled hearings, attend the Accompanied Site Inspection(s) and submit written representations. In addition to this, you can request that the Examining Authority holds an Open Floor Hearing where you can raise concerns about the project, which can include those set out in your email.


attachment 2
attachment 2
attachment 1
attachment 1