Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

North Wales Connection

30 August 2018
Jonathan Dean

Enquiry

Enquiry (from Jonathan Dean by email on 22 August 2018):
I understand from National Grid that PINS conducted a consultation on the SoS Scoping Opinion. Please could I have more details of that consultation as I do not recall being consulted.

Advice given

Response (by email on 30 August 2018):
Under the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009 that were in force at the time of the scoping request for the North Wales Connection (but have since been replaced by the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017), the Planning Inspectorate was required to consult with the person who made the request and the consultation bodies prior to adopting a scoping opinion.
Consultation bodies are defined under the EIA Regulations as:
•a body prescribed under s42(1)(a) of the PA2008 (duty to consult) and listed in column 1 of the table set out at Schedule 1 to the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations where the circumstances set out in column 2 are satisfied in respect of that body;
•each authority that is within s43 of the PA2008 (local authorities for purposes of s42(1)(b)); and
•if the land to which the application, or proposed application, relates or any part of that land is in Greater London, the Greater London Authority.
The Planning Inspectorate conducted this consultation upon receipt of the North Wales Connection scoping request in May 2016. The consultation bodies are detailed in Appendix 2 of the Scoping Opinion.
The Planning Inspectorate’s approach to identifying scoping consultation bodies is detailed in Advice Note three: EIA consultation and notification.