Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

Wylfa Newydd Nuclear Power Station

14 November 2018
Jonathan Dean

Enquiry

What is the process for considering the aggregate impact of non material change requests that may, in aggregate, become material?
Many thanks
Jonathan

Advice given

Dear Mr Dean
Thank you for your email.
In relation to your query, there is no legal definition of ‘material’ but the tests to apply are whether the change is substantial or whether the development now being proposed is not in substance that which was originally applied for. The former constitutes a material change which – provided there is sufficient time remaining in the Examination stage - can be accommodated as part of the Planning Act 2008 (PA2008) process. The latter constitutes a different project for which a new application would be required.
Whether a proposed change falls within either of these categories is a question of planning judgment which may be based on criteria including, for example, whether the change would generate a new or different likely significant environmental effect(s). Similarly, whether (and if so the extent to which) a change request involves an extension to the Order land, particularly where this would require additional Compulsory Acquisition powers eg for new plots of land and/ or interests. Further information about making a material change request can be found in paragraphs 109 to 115 of the Examination Guidance.
attachment 1
The submission of new or revised information before the Examination starts or during the Examination does not necessarily constitute a request to materially change an application. For example, following a decision to accept an application for examination, applicants are often issued with advice by the Planning Inspectorate which may identify errors, omissions and qualitative issues relating to the submitted application documentation. In response applicants may submit errata, amended application documents, plans or environmental information. During the course of the Examination the Examining Authority (ExA) may also request further information or written comments from an applicant or any Interested Party; new information may also be provided in response to an ExA’s written questions. Changes to the application documents may not necessarily result in changes to the underlying project.
The ExA is ultimately responsible for deciding whether new information submitted into the Examination by an applicant constitutes a material change to the application.
Further information about change requests can be found in the Inspectorate’s Advice Note Sixteen: How to request a change which may be material