Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

North Wales Connection

15 March 2018
Jonathan Dean

Enquiry

I assume it is your role to ensure that National Grid adhere to NETS SQSS. Please can you confirm this for me.

Advice given

If National Grid’s application is accepted for examination the Examining Authority (ExA) will conduct the examination in accordance with Planning Act 2008: Guidance for the examination of applications for development consent and assess the proposed development against the policy requirements of the energy National Policy Statements (NPS) EN-1 Overarching and EN-5 Electricity Networks Infrastructure. The ExA will examine the need for the project, any alternatives and assess whether there are any adverse impacts that outweigh the benefits of the project.